Table 8 - ESC maintenance requirements.
ESC Measure Maintenance Trigger Timeframe for Completion
of Maintenance
Sediment basins When settled sediment exceeds Within 7 days of the
the volume of the sediment inspection.
storage zone
Other ESC measures The capacity of ESC measures By the end of the day.
falls below 75%.
Sediment accumulation on ESC devices is to be removed and disposed of to the satisfaction of Noosa
Council.
5 CO N CLU S IO N
This SWMP outlines how stormwater runoff from the site will be managed in order to not adversely
impact the receiving environment.
The proposed lawful point of discharge for the development shall be the existing kerb and channel
within Clipper Street. Stormwater detention is not considered to be required for the development site.
Stormwater runoff will need to be collected on site and directed to the lawful point of discharge at the
build phase to ensure no adverse impacts to neighbouring properties as a result of the development.
Stormwater treatment should be managed through the implementation of best management practices
on site. Based on the scale of the proposed development, and typical pollutants produced, these
measures are considered adequate.
By implementing the proposed stormwater management system, and providing adequate maintenance,
the downstream environment and neighbouring properties will not experience any adverse deterioration
of water quality as a result of the proposed development.
10
Document Set ID: 23959990
Version: 1, Version Date: 23/07/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.