Minor Change Report MCU21 0027 02 & OPW21 0047 02 [As Published] · MCU21/0027.02
The amended stormwater design is accepted by Council subject to an alteration to the On
Maintenance Condition resulting from the use of poly pipes within the verge, to become Council’s
asset.
On Maintenance
2. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy and the draft departmental guideline for the use
of polypropylene and high-density polyethylene pipe for stormwater prior to commencement
of the use. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
a. Certification that all works have been undertaken and completed in accordance with
the requirements of this Permit;
a. As Constructed details in accordance with Council’s Planning Scheme Policy;
b. Maintenance and operational manuals for all proprietary or site specific devices.
c. A 12-month minimum maintenance period for civil works that would not be impacted
by a failure of the alternate poly pipe types.
d. A 5-year minimum maintenance period for civil works that would be impacted by a
failure of the alternate poly pipe types. Note that works “impacted” includes, but is not
limited to, the road formation, pathways, kerb and channel etc. that have poly pipes
below.
4. CONSULTATION
4.1. Referral Agencies
Not applicable
4.2. Internal Council Referrals
The application was forwarded to the following internal Council officers for review and/or comment:
• Infrastructure Services – General advice/approval was sought from the team (Ben
L’Huillier) as to if an additional stormwater pit and the amended layout would be accepted
in principle as a Council asset considering the constraints with the alignment of the existing
services along the development frontage.
5. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme and
does not raise any significant issues that cannot be addressed by reasonable and relevant
conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application OPW21/0047.02, to make a minor change to an existing approval for
Development Permit for Operational Works for Stormwater, drainage works, earthworks and
landscaping situated at 30 & 32 James St Noosaville Qld 4566 described as Lots 3 & 4 RP 72986,
Council on 16 June 2021 decided to:
A. Approve the change.
B. Amend OPW21/0047 Condition 1 and Condition 45 to read as follows:
Page 6 of 8
Document Set ID: 22627320
Version: 2, Version Date: 19/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Report MCU21 0027 02 & OPW21 0047 02 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.