Attachment C Current Development Approval

of 105

Page text read automatically using OCR, there may be inaccuracies

                      b.      bioretention devices which:
                              i.       are designed generally in accordance with the Bioretention Technical Design
                                       Guidelines (Water by Design, 2012)
                              ii.      are designed generally in accordance with IPWEQA Standard Drawing No. DS-
                                       073, DS-075, DS-076, and DS-078
                              iii.     are provided with a free-draining outlet from the sub-soil drainage system
               44.    Permanent educational signage must be erected to educate the residents of the development
                      about the function of the bioretention device(s). The dimensions, standard, presentation and
                      location of the educational signage must be in accordance with an Operational Works
                      approval.
               45.    All stormwater quality treatment devices must be maintained in accordance with the Water
                      by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The approved
                      Operational Works drawings for the stormwater quality treatment system and detailed life
                      cycle costing of the system must be attached as an addendum to this document. Records of
                      all maintenance activities undertaken must be kept and made available to Council upon
                      request.
               46.    Any proposed Community Management Statement required for the development must
                      include Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1) and
                      must include the full cost of maintaining the system in accordance with Water by Design
                      (2009) Maintaining Vegetated Stormwater Assets (Version 1). The cost of maintaining the
                      system must be included in the proposed levies for each unit owner.
                      Landscaping Works
               47.    The development site must be landscaped. The works must be undertaken in accordance
                      with an Operational Works approval and the Noosa Plan for that specific area and Planning
                      Scheme Policy (PSP2) - Landscaping and must include in particular:
                      a.      the works shown on the Approved Plans with the exception of substituting
                              Archontophoenix cunninghamiana (Bangalow Palm) for an appropriate species
                              selected from the Noosa Plan 2020 PSP20 Landscaping policy or endemic to Noosa.
                              Palms are not appropriate for this location (see section 6 of PSP2 – Landscaping.
                      b.      a 6 metre wide planted buffer, consisting of local native plant species suitable for the
                              location, as shown on the Approved Plans and as required by condition 53 of
                              RAL18/0023;
                      c.      the provision of mature landscaping of varied mature heights (between 2 to 6 metres),
                              within appropriately designed deep planter boxes at podium level between Buildings
                              A&B
                      d.      protection of vegetation within the 10 metre wide Environmental and Conservation
                              Zone;
                      e.      vegetation installed for landscaping adjacent to the 10 metre wide vegetation strip
                              protected by the Environmental and Conservation Zone and Covenant J must only
                              include Noosa native species and not include any of the undesirable species as
                              detailed within the Noosa Plan 2020 – Scheme Policy 3 Landscaping;
                      f.      the use of large tree species to provide visual screening of the bulk of the buildings
                              from Hofmann Drive and provide shade to the units from the afternoon sun, including
                              100 litre specimens;
                      g.      vegetated screening of any electrical transformers, bin storage areas and the like from
                              the road frontage;
                      h.      provision of 1 advanced or ex-ground street tree within the road reserve for every 8
                              metres of road frontage; and
                      i.      control of all weed species listed in the following standards and legislation:

                                                                                                          Page 9 of 24

Document Set ID: 22110072
Version: 4, Version Date: 21/09/2022

Log in to download the original (Attachment C Current Development Approval.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.