Attachment C Current Development Approval

of 105

Page text read automatically using OCR, there may be inaccuracies

               28.    Provide certification from an appropriately qualified acoustic consultant prior to Certificate of
                      Classification that the residential buildings have been constructed in accordance with the
                      requirements of the Approved Acoustic Report (Acoustic Logic report dated 23.09.21) and
                      the measured internal noise levels in respect to road traffic noise comply with the
                      AS2017:2016 levels in Section 4.4 of the approved acoustic report.
               29.    Provide certification from an appropriately qualified consultant that mechanical ventilation or
                      air-conditioning has been installed in all habitable rooms affected by road traffic noise as
                      identified in Section 6.5 and Appendix C of the Approved Acoustic Report (Acoustic Logic
                      Report dated 23.09.21).
                      Mechanical Plant Noise
               30.    Design and install all mechanical plant as part of the development to comply with Section 7.1
                      and Table 22 of the Approved Acoustic Report (Acoustic Logic Report dated 23.09.21)
               31     Provide certification from an appropriately qualified acoustic consultant prior to Certificate of
                      Classification that the mechanical plant has been installed with the requirements of the
                      Approved Acoustic Report (Acoustic Logic report dated 23.09.21) and the measured noise
                      levels of operational plant comply with Table 22 of the Approved Acoustic Report (Acoustic
                      Logic Reported dated 23.09.21).
               ENGINEERING/TRAFFIC
                      External Works
               32     Hofmann Drive must be upgraded for the length of its frontage to the subject site. The works
                      must be undertaken in accordance with an Operational Works approval, completed prior to
                      the commencement of the use and must include in particular:
                      a.      construction of a pedestrian footpath in accordance with the conditions of this Decision
                              Notice
                      b.      removal of all existing property access (driveway/crossovers) and reinstatement of the
                              kerb, footpath and verge area to match the balance of the site frontage, including the
                              provision of topsoil and turf where the existing verge is grassed
                      Site Access and Driveways
               33.    A sealed access driveway must be provided from the formation in Hofmann Drive to all
                      parking and manoeuvring areas of the development. The works must be undertaken in
                      accordance with an Operational Works approval and must include in particular:
                      a.      a driveway crossover generally in accordance with Council standard drawing RS-051
                              and any associated addendums
                      b.      access aisles and ramps in accordance with AS/NZS2890.1:2004 Parking Facilities
                      Car Parking, Pedestrian and Bicycle Facilities
               34.    A maximum of 134 car parking spaces must be provided and marked on the site and made
                      available and accessible at all times. The works must be undertaken in accordance with an
                      Operational Works approval and must include in particular:
                      a.      Minimum 9 visitor parking spaces and 4 motorcycle/scoter spaces within the total,
                              which are clearly marked for that purpose and accessible at all times for visitor use.
                              These spaces must be located outside of the basement.
                      b.      3 disabled parking space within the total
                      c.      dimensions, crossfalls and gradients in accordance with Australian Standard
                              AS/NZS2890.1:2004 Parking Facilities
               35.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with an Operational Works approval and must include a 2 metre
                      wide concrete footpath within the Hofmann Drive road reserve extending across the full
                      frontage of the sites and connecting to the new pathway to the east of the site.

                                                                                                        Page 6 of 24

Document Set ID: 22110072
Version: 4, Version Date: 21/09/2022

Log in to download the original (Attachment C Current Development Approval.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.