Attachment C Current Development Approval
This condition is imposed pursuant to s145 of the Planning Act 2016 being necessary trunk
infrastructure identified by Council’s LGIP to service the development.
36. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction
i. maintenance of safe pedestrian access for the areas affected by the works during
and after daily construction has ceased
ii. proposed fencing to the site during the construction phase of the development
iii. approval of the Traffic Management Control Plan by the Department of Transport
and Main Roads (DTMR) for any works on State controlled roads
iv. provision for worker car parking
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures
c. works programme identifying key components of the works and their respective
durations
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic, services and other relevant issues.
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
h. details on the location of external fill/dump sites/sources, the haulage route, type of
vehicle to be utilised during filling operations and frequency of usage. NB any damage
to the existing road system as a result of haulage operations shall be fully repaired at
the applicant’s expense
i. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Easements
37. Unless otherwise agreed in writing by the relevant service provider, any public or third-party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
38. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
39. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Page 7 of 24
Document Set ID: 22110072
Version: 4, Version Date: 21/09/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Attachment C Current Development Approval.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.