ATTCH 2 - IR Response - Ecological and Bushfire IR Response (Cardno)
Attached to the e-mail RAL17/0501 IR Response email 1 of 4.
The original of this document is very large (15.3 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Original PDF page 36, section 1. The text section number identifies this passage in the reader.
Bushfire Management Plan
Lot 71 on MCH 2854, Castaways Beach
The building setbacks required to achieve each of the AS3959 (2009) BAL standards are summarised in Table
5-1.
Table 5-1 Bushfire Attack Level Setback Assessment – Bushfire Prone Areas
Minimum Building Setback
AS3959 (2009)
Risk description as per AS3959 (2009) Required (m)
BAL Category
Low The risk is considered to be VERY LOW. 100
There is insufficient risk to warrant any specific
construction requirements under AS3959.
12.5 The risk is considered to be LOW. 34
There is a risk of ember attack.
Construction elements are expected to be exposed to a
heat flux not greater than 12.5 kW/m2.
19 The risk is considered to be MODERATE. 24
There is a risk of ember attack and burning debris
ignited by wind borne embers and a likelihood of
exposure to radiant heat.
Construction elements are expected to be exposed to a
heat flux not greater than 19 kW/m2.
29 The risk is considered to be HIGH. 16
There is an increased risk of ember attack and burning
debris ignited by wind borne embers and a likelihood of
exposure to an increased level of radiant heat.
The construction elements are expected to be exposed
to a heat flux not greater than 29 kW/m2.
40 The risk is considered to be VERY HIGH. 12
There is a much increased risk of ember attack and
burning debris ignited by windborne embers, a
likelihood of exposure to a high level of radiant heat and
some likelihood of direct exposure to flames from the
fire front.
The construction elements are expected to be exposed
to a heat flux not greater than 40 kW/m2.
Flame Zone - FZ The risk is considered to be EXTREME. < 12
There is an extremely high risk of ember attack and
burning debris ignited by windborne embers, and a
likelihood of exposure to an extreme level of radiant
heat and direct exposure to flames from the fire front.
The construction elements are expected to be exposed
to a heat flux greater than 40 kW/m2.
Each of the proposed Lots has a defined Building Envelope as shown in Drawing Ref WE17035-BAR-001
presented in Appendix D. The nearest of these Building Envelopes to designated Bushfire Hazard Areas is
WE17035 | 13 November 2017
11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.