NOOSA COUNCIL IDAS Development Application Decision Notice                                                   6 of 15


      Water Supply          $4,439
      Sewerage              $7,008
      TOTAL                 $11,447
      All headworks contributions must be paid prior to the issue of a Development Permit for Operational
      Works.
      Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the headworks
      contributions not be paid at the due time, Council shall call upon the trading bank guarantee in full.
      In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
      the contribution or trading bank guarantee will be returned.
      Earthworks
34.   Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
      structures that border the development site. Fences that are affected shall be replaced prior to the
      Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced shall be
      clearly shown on the plans submitted for Operational Works approval.
      Site Stability
35.   A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site, determine the
      soil classification, establish whether any measures are required to protect the stability of adjoining
      buildings and/or structures, and make recommendations on the type of foundation system(s) best suited
      for the proposed development. This information shall be submitted to the Council for assessment and
      approval prior to obtaining a Development Permit for Operational Works.
Erosion and Sediment Control
36.   Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
      control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
      waste, will be necessary.
     In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
     to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
37.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be submitted in
      conjunction with an application for a Development Permit for Operational Works. In this regard a
      DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction
      with any application for Operational Works.

38.   Digital detailed design drawings and calculations shall be submitted with any application for a
      Development Permit for Operational Works in respect of roadworks and stormwater drainage works. To
      avoid conflict with underground pipes or services, all existing and proposed services required by the
      development shall be shown on the plans.

39.   To facilitate production of As Constructed drawings it is suggested that all design drawings are submitted
      in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are
      available at www.adac.com.au).

40.   Any damage caused to any public utility during the course of construction shall be repaired to Council’s
      standards and at no cost to Council.

41.   Any alteration of any public utility or other facilities necessitated by the development of the land or
      associated construction works external to the site shall be at no cost to Council.

42.   The transportation of all materials to and from the site shall be undertaken in a manner such that no
      particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
      be covered to prevent materials including dust being windblown from the vehicle.

43.   As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer for design
      intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all services
      and structures. All of which shall be submitted to Council for checking and for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage structures,
      finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
      As Constructed (ADAC) digital format.            (Guidelines on the use of ADAC are available at
      www.adac.com.au).




SCRC c:\docume~1\dwallace\locals~1\temp\bcl technologies\easypdf 5\@bcl@e80b781d\@[email protected]

Used in these records

About this file

File size
168 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_402 SUPERSEDED Decision Notice [As Published].pdf · 168 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.