6 May 2022


Noosa Council
[email protected]


RE:     Response to COuncil Meeting Further Advice RAL21/0033 – 60 Glenridge Dr
        Cooroibah Qld 4565


Council discussed the application at its General Committee Meeting on 19 April 2022. The
applicant provides the following additional information in response to condition 2 (a-i) of
the recommended preliminary approval:

Condition 2 - Amended plans and reports must be submitted to Council prior to any
further development applications being made and must include the following:

      A. Amend subdivision layout (Plan: 21598-P001 Rev B, 21598-P003 Rev C)
         detailing amalgamation of Lots 1 and 2.
      B. Amend the subdivision layout and include the mapped Koala Habitat
         adjacent to Mckinnon Drive in one lot.

An amended plan of subdivision has been drafted including the following changes:
   -    8 lot subdivision
            o No changes to lot 8 (Stage 1).
            o Amalgamation of previous lot 1 and 2 adjoining Glenridge Dr.
            o Changes to lots 2-7 at the end of the cul-de-sac head (additional lot and
                house site area).
            o Proposed lot 3 includes all koala habitat mapped vegetation in one lot.
   -    Amended covenant and house site areas (all 1,100m2)
   -    Emergency access through to Mckinnon Dr
Log in to download the original file

6.5.22 - Further advice response 6 may.pdf · 2.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 4 pages

Page 2

    C. Update the fill level for the building envelope of proposed Lot 8 to the PMF
       Level.

Lot 8 to include a 1,100m2 fill envelope (adjacent to the existing house) above the PMF.
The Flood Investigation modelling has been remodelled to accommodate the changes in
the subdivision design and all lot envelopes are above the PMF, while also having no
impact to adjoining properties.


    D. Provide a Risk Assessment Report that demonstrates compliance with PO7
       and AO7.1 to AO7.3 of the Flood Hazard Overlay Code and addresses
       management of risks to occupants of the site having regard to Mckinnon
       Drive being not trafficable during a PMF event.
    E. Amend Table 4-5 of the Flood Investigation – 60 Glenridge Dve, Cooroibah
       Version 4 prepared by PeakUrban dated 01/04/2022 to address the
       following:
          i.  The minimum fill level for proposed Lot 8 is to be amended to the
              PMF level. All works are to be carried out generally in accordance
              with the updated flood investigation report.
         ii.  The updated flood investigation report is to be submitted to Council
              for approval prior to the issue of Development Permit.

Brendon Bolt from Peak Urban Consulting Hydraulic Engineers provides an updated
section in the Flood Investigation Report (4.3.2.8) discussing the Flood Risk from the site.
The relevant section of the report is included below (highlight’s emphasis) as well as the
GCCC Flood Refuge Guideline:
       4.3.2.8.Flood Risk
       This development has been designed to provide flood free access to all lots via the new internal road
       in events up to the 10% AEP and will remain trafficable in events up to the 1% AEP event in
       accordance with the Queensland Urban Drainage Manual (QUDM). Further consideration of flood
       risk has been undertaken in events greater than the 1% AEP event, with assessment of the PMF
       event taking place. The assessment found that the lots within the development would become
       isolated in extreme events such as the PMF, with the internal access road having flow conditions that
       would not be trafficable.
       An assessment was completed as to the length of time the internal access would be considered not
       trafficable (flow depths> 0.2m) along the warning time between the start of the rain event to when
       the internal crossing becomes not trafficable. The assessment was completed for the PMF event for
       a number of durations and is highlighted below. From this, it is considered that a site flood warning
       system would not be appropriate in this situation due to the short response times for flood waters to
       rise. It would be safer outcome for residents to seek refuge within their houses and communication
       about a extreme weather system come from Council or State Disaster Management Services.
       This assessment highlights that there would be a limited amount of time to warn / evacuate residents
       due to the relatively short amount of time it takes for the internal road to become inundated in an
       extreme (i.e PMF) event. This would be typical of all catchments where the upstream catchment is
       relatively small. From this, the time of submergence is also relatively small with times ranging from
       2.0 to 8.0 hours depending on the event duration. From this, it is considered that the provision of
       suitable flood refuge or evacuation to higher ground (i.e.to Glenridge Drive) would be the preferred
       risk management measure as opposed to evacuating the area to a formal evacuation centre. Each
       lot is provided with an1,100m2 building envelope above the PMF level that would be suitable to act
       as a flood refuge until flood waters recede. The application of a flood refuge is recommended in
       similar circumstances as means to address flood risk and potential burden by Gold Coast City Council
       (GCCC), who have large amount of flood plain on which developments are managed. The Guideline
       developed by GCCC is presented in Appendix J, and in summary states “a shelter-in-place
       approach” provides an opportunity to address the risks of isolation and subsequent risk to life and
       potential burden to emergency services and has been commonly used in development assessment
       for larger developments”. Further to this, that subsequent that Council Disaster Management Plan
       includes communications to these future residents that their building envelopes serve as a flood
       refuge should anevent greater than the 1% AEP event occur. This information could also be
       conveyed via property note.




                                                                                             Page 2 of 5

Page 3

    F. Provide an effluent disposal report demonstrating that the house site areas
       can sustain appropriate disposal areas.

Please find attached on-site effluent disposal report prepared by Waterwise Design. The
soils are categorised as category 5 clays, using a 4-bedroom model for 6 people per site
with an AES effluent disposal system recommended within each of the building envelopes.




                                                                            Page 3 of 5

Page 4

    G. Provide a fencing plan that details:
         i.  no fencing within the covenant area
        ii.  no fencing or gates restricting access between lots in relation to the
             fire break trail areas.

Please find attached an updated fencing plan in compliance with conditions 10i
(covenants), 32 (fencing design) and 39 (fire break easement) of the preliminary approval
conditions. Only star pickets are to delineate boundaries within the covenant area and
access is provided for between the covenant vegetation and the building envelopes.
An updated bushfire and ecological rehabilitation plan will be supplied by Monday (9 May).




    H. Investigate the provision of a temporary fire/emergency access to
       Mckinnon Drive.

An emergency access has been incorporated into the revised subdivision design at the
behest of Councillors. An amended response from DTMR and SARA has been requested.

    I.   Investigate the provision of an access road above the 1% AEP flood level

This development has been designed to provide flood free access to all lots via the new
internal road in events up to the 10% AEP and will remain trafficable in events up to the
1% AEP event in accordance with the Queensland Urban Drainage Manual (QUDM).
Brendon Bolt RPEQ and Doug Reynolds RPEQ consider this is in accordance with The
Noosa Plan requirements and engineering standards.




                                                                             Page 4 of 5

Page 5

Pursuant to the Development Assessment Rules, the applicant has given the assessment
manager the further advice requested. Please proceed with your assessment of the
application at your earliest convenience.

If you have any further queries in relation to the above, please do not hesitate to contact
myself.

Regards,




Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA MQELA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227




                                                                              Page 5 of 5

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.