16.      Bicycle facilities in accordance with AS2890.3 Bicycle Parking Facilities must be
         provided for the development. The facilities must be indicated on the plans and
         submitted in accordance with an Operational Works approval and must include in
         particular:
         (a)        a total of 19 bicycle parking spaces
         (b)        end of trip facilities involving a minimum of 10 lockers and 1 shower
                    cubicle with an ancillary change room.
          Earthworks and Retaining Walls
17.      All retaining walls must be designed and constructed in accordance with the
         planning scheme and must be certified by an RPEQ where exceeding 1.0m in
         height.
HYDRAULICS AND WATER QUALITY
          Stormwater Drainage
18.       The site must be provided with a stormwater drainage system connecting to a
          lawful point of discharge. The works must be undertaken in accordance with an
          Operational Works approval and QUDM, and must include in particular:
          (a)       the works shown on the Referenced Plans listed in this Decision Notice
          (b)       collection and discharge of stormwater to the existing stormwater
                    easement along the frontage of the site.
          (c)       the use of gravity stormwater drainage and not surcharge pits.
          Stormwater Quality Management
19.       A stormwater quality treatment system must be provided for the development.
          The works must be undertaken in accordance with an Operational Works
          approval and the Bioretention Technical Design Guidelines (Water by Design ,
          20 12), and must include in particular:
          (a)       stormwater quality treatment devices of a size and location generally in
                    accordance with those shown on the integrated water cycle management
                    plans listed in this Decision Notice
          (b)       bioretention devices which :
                    (i)       are designed generally in accordance with IPWEQA Standard
                              Drawing No. WSUD-001
                    (ii)      are provided with a free-draining outlet from the sub-soil drainage
                              system
20 .      Permanent educational signage* must be erected to educate the customers to
          the development about the function of the bioretention device(s).           The
          dimensions, standard, presentation and location of the educational signage must
          be in accordance with an Operational Works approval.
          *(Refer to Advisory Note)
21.       All stormwater quality treatment devices must be maintained in accordance with
          the Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version
          1). The approved Operational Works drawings for the stormwater quality
          treatment system and detailed life cycle costing of the system must be attached




PD-DA-FM1420s/4-0 1/10/2013                                                              Page 4 of 11

Used in these records

About this file

File size
436 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

4. MCU130098 Decision Notice (approval).pdf · 436 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.