Log in to see the plans as drawn8. ANNEX A: Levels of Service
8.1 Sealed Roads – Service Level Catalogue
Service Output ROAD NETWORK
Provision and maintenance of an integrated, safe and serviceable
road transport network comprising roads, bridges and car
parking.
Service Activity Sealed Roads
The activities include repairs to the road surface, shoulders and
table drains as well as maintenance of allied road furniture such
as guardrails, barriers and other structures, streetscape furniture
& fittings, providing and maintaining signage and line-marking
and street sweeping/cleaning.
Responsible Area Department Branch
Infrastructure Services Civil Operations Branch (Civil
Works & Maintenance)
Cost Centres Sealed Roads 2001
Hastings St Maintenance Levy 2022
Signs & Lines 2003 (actual costs captured
to WO Cost Centre 2001)
Road Furniture 2006 (as above)
Vegetation 2008 (as above)
Traffic Operations 2012
Department Management – Director 1900
Infrastructure Services
Management Civil Operations 2000
Works Operations Coordination 2021
Works Operations 2704
Key statistics i 670 km of sealed road
Legislative responsibility to Local Government Act 2009
provide this service Land Act 1994
ACTIVITY SERVICE LEVEL TARGET
Road surface maintenance
(Defects monitoring, pothole patching & pavement repairs, road shoulder & table drain maintenance)
Cyclic Inspections Scheduled surface/pavement Six monthly
inspections in all Work Zones
In addition ad hoc inspections are
undertaken in conjunction with regular
patrol patching maintenance
Scheduled work ii As identified from inspections (defects & proactive interventions) to
maintain asset serviceability other than as identified below.
Hastings St additional works (levy)
Pressure washing coloured concrete Twice a year / levy covers 1
zones (includes pedestrian crossings extra service
and some footpath areas)
Reactive work (customer Issue Target days (to advise
requests) iii customer of outcome)
All maintenance requests 20 business days
Removal of dead animal from roads 3 business days
Asset Management Plan: Roads Infrastructure Page 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.