2018-12-11 S&O Agenda - Attachment 1 to Item 16 - Road Infrastructure Asset Management Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn 8.3 Carparks – Service Level Catalogue
Service Output ROAD NETWORK
Provision and maintenance of an integrated, safe and serviceable
road transport network, including roads, bridges and car parking.
Service Activity Car Parks
The activities include surface and kerb repairs, maintenance of
signs and line marking as well as street sweeping/cleaning.
Responsible Area Department Branch
Infrastructure Services Civil Operations Branch (Civil
Works & Maintenance)
Cost Centres Car Parks 2011
Department Management – Director 1900
Infrastructure Services
Management Civil Operations 2000
Works Operations Coordination 2021
Works Operations 2704
Key Statistics xii Approx. 49 off-road car parks with estimated 2,492 parking spaces
Legislative responsibility to No.
provide this service However, there is a community expectation that local government
provide adequate car parking.
ACTIVITY SERVICE LEVEL TARGET
Maintenance
(Inspections and maintenance to provide a serviceable and clean pavement, appropriate line marking and
signage)
Cyclic Inspections Car Parks Coastal (pavement/kerbs) Precinct areas quarterly others
Car Parks Hinterland (pavement/kerbs) annually
Car Parks Signs & Lines (Coastal & Part of above inspection
Hinterland) xiii
Scheduled works As identified from inspections (defects & proactive interventions) to
maintain asset serviceability. xiv
Street Cleaning
(Scheduled and reactive mechanical and manual cleaning of sealed street pavements and kerbs in urban
areas to provide good amenity, reduce risk of stormwater drainage blockages, and help protect water quality
in our rivers by reducing the amount of debris and leaves that enter stormwater drainage)
Cyclic Inspections Cleaning contracts audit (sites selected Monthly
ad hoc)
Scheduled work Mechanical street sweeping Frequency (approx.)
(Contract) xv
• The Maze car park – Hastings Fortnightly
St/Noosa Drive
• Wallace Park Monthly
• Tewantin Boat Ramp Carpark
Manual street cleaning/litter pick-up
(Contract) xvi
• Peregian Beach; Sunshine Beach; Daily
Sunrise Beach; Noosa Junction;
Noosa Heads; Noosaville &
Tewantin
• Boreen Point & Cooroy 3 x week
Asset Management Plan: Roads Infrastructure Page 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.