                                                         Officer:                  Glen Conforti
                                                         Direct Telephone:         07 53296241
                                                         Our Reference:            GCONFORTI:MCU13/0247.01
                                                         Your Reference:           13075/16134ms.ms
               2 June 2015



               Bell-Allen Holdings Pty Ltd
               C/- DFS Group
               PO Box 605
               MAROOCHYDORE QLD 4558

               [email protected]


               Dear Sir/Madam




                                       Change to an Existing Approval
                                             Sustainable Planning Act 2009

               I refer to your request to make a permissible change to an existing approval. On 1 June 2015,
               Council decided your requested changes.

               Details of the decision are as follows:
               1.     APPLICATION DETAILS

               Application No:                 MCU13/0247.01
               Street Address:                 56 Seaview Tce SUNSHINE BEACH QLD 4567
               Real Property Description:      Lot 64 RP 81810
               Planning Scheme:                The Noosa Plan (16 September 2013)
               2.     DECISION DETAILS
               Council on decided to issue the following type of approval:
               •      Development Permit for a Material Change of Use (Detached House)

               In relation to the request to make a change to the existing approval, Council on 1 June 2015
               decided to:
               A.     Approve a change to Condition 2
               B.     Include additional Conditions 16, 17, 18, 19 & 20
               C.     Delete Item 6 (Approved Plans) and renumber Items accordingly

               3.     RELEVANT PERIOD OF APPROVAL
               The relevant period for this development approval is in accordance with that stated in the
               Decision Notice dated 20 January 2014, unless an application to extend the period is
               approved by Council under s 383 of the Sustainable Planning Act 2009.


                                             PO Box 141                      P. (07) 5329 6500   [email protected]
                                             TEWANTIN QLD 4565               F. (07) 5329 6501   www.noosa.qld.gov.au

Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015
Log in to download the original file

DF15035_Bell Allen_Change to Existing Approval Decision Notice_090916.pdf · 234 KB (small file)

Full text of the other 6 pages

Page 2

                                                                                                   MCU13/0247.01



               4.     CONSOLIDATED ASSESSMENT MANAGER CONDITIONS
               PLANNING
               When Conditions must be Complied With
               1.     Unless otherwise stated, all conditions of this Decision Notice must be complied with
                      prior to the use commencing, and then compliance maintained at all times while the
                      use continues.

               Approved Plans
               2.     Development undertaken in accordance with this approval must generally comply with
                      the approved plans of development. The approved plans are listed in the following table
                      unless otherwise amended by these conditions.


                      Plan No.         Rev. Plan Name                                                    Date
                      A-01             18   Proposed Ground Floor, prepared by Harry Poulos              04.05.15
                                            Architects
                      A-02             14   Proposed 1st Floor Street Entry Level, prepared by Harry     05.05.15
                                            Poulos Architects as annotated by Council
                      A-03             07   Proposed 1st Floor Plan, prepared by Harry Poulos            22.04.15
                                            Architects
                      A-04             06   Proposed Roof & Site Plan, prepared by Harry Poulos          (Rev. 05)
                                            Architects as annotated by Council                           29.03.15
                      A-05             08   Proposed Front Elevation, prepared by Harry Poulos           18.03.15
                                            Architects
                      A-06             10   Proposed RHS (South) Elevation, prepared by Harry            05.05.15
                                            Poulos Architects as annotated by Council
                      A-07             10   Proposed Rear (East) Elevation, prepared by Harry Poulos 05.05.15
                                            Architects
                      A-08             11   Proposed LHS (North) Elevation, prepared by Harry            05.05.15
                                            Poulos Architects
                      A-10             12   Section A-A, prepared by Harry Poulos Architects             04.05.15
                      A-11             14   Section B-B (NGL shown – 4m from LHS Boundary),              27.03.15
                                            prepared by Harry Poulos Architects

               Building Height
               3.     The maximum height of the development must not exceed 8 metres above the finished
                      ground level and the natural ground surface and 2 storeys.

               4.     Certification must be submitted to Council from a Licensed Surveyor which certifies
                      that the building does not exceed the maximum height requirement of this Decision
                      Notice.




                                                                                                       Page 2 of 7


Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015

Page 3

                                                                                                 MCU13/0247.01


               Performance Bond
               5.     Security in the form of a cash bond or trading bank guarantee to the sum of $5000
                      must be submitted to Council, to secure performance of all conditions of this
                      approval, prior to the issue of a Development Permit for Building Works. The cash
                      bond or trading bank guarantee will be returned on performance of the conditions of
                      approval less any costs incurred by Council in respect of enforcing performance of this
                      permit. Council reserves the right to call upon the bond or guaranteed sum to effect
                      compliance with conditions.

               Landscaping
               6.     A minimum of 20% of the site must be retained as soft landscaping.

               7.     Existing trees on the site must be retained, except where required to be removed to
                      accommodate the approved dwelling. In this regard, the removal of vegetation must not
                      extend beyond 3 metres of the building footprint.

               8.     Trees to be retained must be protected from clearing or construction activities by:

                      (a)     clearly marking vegetation to be retained with flagging tape
                      (b)     installing protective fencing around the drip line of the vegetation
                      (c)     restricting stockpiling, storage and vehicle parking to those areas high are
                              already cleared
                      (d)     using low impact construction techniques around vegetation

               Drainage and Earthworks
               9.     Fill material placed over services must not impose any additional surcharge loading on
                      the service.

               10.    Excavation must not be carried out within 600mm of any utility infrastructure (to top,
                      sides and base of services). A retaining wall must be provided to support the soil
                      surrounding utility infrastructure where proximate to excavation activities.

               11.    Compaction with a vibrating roller must not be carried out within 600mm of any utility
                      infrastructure.

               Geotechnical Stability
               12.    All works must be carried out in accordance with the Geotechnical Investigation
                      prepared by Golder Associates listed within this Decision Notice.

               Coastal Protection
               13.    Gates must not be installed along the rear property boundary to gain direct access to the
                      beachfront.

               14.    Landscaping consisting of native ground covers, shrubs and trees must be planted for a
                      width of 2m from the rear seaward boundary in accordance with Council’s Planning
                      Scheme Policy PSP3 Landscaping Plants and Guidelines.

               15.    External colours and finishes of the building must comprise of muted/environmental
                      tones that blend with the natural environment.




                                                                                                  Page 3 of 7


Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015

Page 4

                                                                                                   MCU13/0247.01

               ADDITIONAL CONDITIONS 1 JUNE 2015

               Roof line
               16.    The roof must not extend seaward of a line drawn between the closest roof corner of the
                      adjoining properties to the north and south as annotated by Council on the approved
                      plan A-02 revision 14.

               Privacy Screens
               17.    The privacy screens located on the 1 first floor seaward deck must not extend beyond
                      the roof line.

               Clothes Drying Deck
               18.    The clothes-drying deck must be setback a minimum of 1m from the boundary. Design
                      options for clothes drying purposes such as external stairs, decks or the like exceeding
                      1m above the NGL must be setback a minimum of 1m.

               19.    Screening vegetation must be planted for the full length of the revised clothes drying
                      deck location/design and the boundary in accordance with Council’s Planning Scheme
                      Policy PSP3 Landscaping Plants and Guidelines. The planted vegetation must have a
                      minimum pot size of 200mm and consist of native, endemic species with a mature height
                      of not less than 4 metres. At maturity the landscaping must effectively screen the clothes
                      drying deck and associated structures from the neighbouring property.

               Undercroft
               20.    The undercroft area must not consist of hard pavement or the like and remain at natural
                      ground level.

               5.     REFERRAL AGENCY CONDITIONS
               Not Applicable

               6.     REFERENCED DOCUMENT

               Document No.            Rev. Document Name                                          Date
               137632184-001-R-        0     Geotechnical Investigation, prepared by Golder        January 2013
                                             Associates


               7.     ADVISORY NOTES
               The following notes are included for guidance and information purposes only and do not form
               part of the assessment manager conditions:
               Equitable Access and Facilities
               The plans for the proposed building work have NOT been assessed for compliance with the
               requirements of the Building Code of Australia – Part D3 as they relate to people with
               disabilities. Your attention is also directed to the fact that in addition to the requirements of the
               Building Code of Australia – Part D3 as they relate to people with disabilities, one or both of
               the following may impact on the proposed building work:
               (a)       The Disability Discrimination Act 1992 (Commonwealth)
               (b)       Anti-Discrimination Act 1991 (Queensland)


                                                                                                     Page 4 of 7


Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015

Page 5

                                                                                                 MCU13/0247.01

               Council recommends that the following matters be considered to address equitable access
               and facilities in the building:
               (a)       The building and environs should be designed to meet the requirements of the Human
                         Rights and Equal Opportunity Commission “Advisory Notes on Access to Premises”
                         and AS 1428.2
               (b)       Applicants should be aware that a “Disability Standard on Access to premises” is
                         currently being developed and most likely will impose changes on the Building Code of
                         Australia
               (c)       Any services and facilities in the building complex should allow independent, dignified
                         and equitable use of the services and facilities for all people.

               Aboriginal Cultural Heritage Act 2003
               There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
               approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
               The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
               carries out an activity must take all reasonable and practicable measures to ensure the activity
               does not harm Aboriginal cultural heritage.” It is an offence to fail to comply with the duty of
               care. Substantial monetary penalties may apply to individuals or corporations breaching this
               duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the
               Minister administering the Act can also issue stop orders for an activity that is harming or is
               likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural
               heritage.
               You should contact the Cultural Heritage Co-ordination Unit on 07 3239 3647 to discuss any
               obligations under the ACH Act.

               8.     PROPERTY NOTES
               Not Applicable

               9.     PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME
               Not Applicable

               10.    FURTHER DEVELOPMENT PERMITS REQUIRED
               •      Development Permit for Building Work (All Building Works)

               11.    SELF ASSESSABLE CODES
               The following codes for self-assessable development related to the development approval
               issued under this Decision Notice must be complied with.
               •      Detached House Driveways Code

               12.    SUBMISSIONS
               Not Applicable


               13.    REASONS / GROUNDS FOR APPOVAL
               Not Applicable




                                                                                                  Page 5 of 7


Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015

Page 6

                                                                                              MCU13/0247.01

               14.     RIGHTS OF APPEAL
               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from
               the Sustainable Planning Act 2009 is attached.

               15.     OTHER DETAILS
               If you wish to obtain more information about Council’s decision, electronic copies of which are
               available on line at www.noosa.qld.gov.au, or at Council offices.


               DECISION NOTICE HISTORY
               Original Decision Notice (20 January 2014)
               Changes to an Existing Approval (1 June 2015),



               Yours faithfully




               GLEN CONFORTI
               DEVELOPMENT PLANNER



               Encl.     Approved Plans/Documents
                         Appeal Rights



               cc        Unitywater




                                                                                                Page 6 of 7


Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015

Page 7

                                                                                                          MCU13/0247.01



                                                           Appeal Rights
                                                           SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING
                                                           REGULATION 2009



               The following is an extract from the Sustainable
               Planning Act 2009 (Chapter 7)


               466       Appeals about decisions             relating   to
                         permissible changes
               (1)       For a development approval given for a
                         development application, the following persons
                         may appeal to the court against a decision on a
                         request to make a permissible change to the
                         approval—
                         (a)       if the responsible entity for making the
                                   change is the assessment manager for
                                   the application—
                                   (i)       the person who made the
                                             request; or
                                   (ii)      an entity that gave a notice
                                             under section 373 or a pre-
                                             request response notice about
                                             the request;
                         (b)       if the responsible entity for making the
                                   change is a concurrence agency for the
                                   application—the person who made the
                                   request.
               (2)       The appeal must be started within 20 business
                         days after the day the person is given notice of
                         the decision on the request under section 376.
               (3)       Also, a person who has made a request under
                         section 369 may appeal to the court against a
                         deemed refusal of the request.
               (4)       An appeal under subsection (3) may be started at
                         any time after the last day the decision on the
                         matter should have been made.




                                                                                                            Page 7 of 7


Document Set ID: 19916238
Version: 1, Version Date: 04/06/2015

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.