PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 25 MARCH 2014
Page 57 of 231
PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 25 MARCH 2014
8. A “no clearing zone” must be established and maintained over the land outside the
development footprint on the Approved Site Plan. The following activities must not be
carried out within the no clearing zone:
(a) clearing, cutting down, poisoning, lopping or pruning of native vegetation which is
indigenous to, or planted within, the zone;
(b) soil/spoil dumping and/or compacting; and
(c) soil excavation, other than for planting indigenous native plants.
The following exceptions apply:
(a) declared plants under the Land Protection (Pest and Stock Route Management) Act
2002 and sub-ordinate Regulation 2003, and any Council Listed Environmental
Weeds, Exotic Grasses and other plants identified in writing by Council;
(b) indigenous native trees which pose a well-founded threat to persons or property as
approved in writing by Council; and
(c) controlled bushfire burns to maintain ecological processes subject to submission of
a Bushfire Management Plan and agreed in writing by Council.
9. The development must be undertaken in accordance with the Rehabilitation and Weed
Management Procedures contained in approved Weed Management and Vegetation
Rehabilitation Plan for the site.
Refuse Management
10. The development must be provided with a refuse container storage area. This area is to
be:
(a) a fully enclosed and roofed area such that animals or vermin cannot access the
waste. In this regard it shall be fully enclosed on three sides using materials
compatible with the site (e.g. palings, lattice work, brick or blockwork, etc), and
provided with access gates or doors to facilitate easy access and removal of refuse
bins;
(b) adequate in size for general refuse bins and recycling bins;
(c) imperviously sealed with a bunded base (e.g. concrete, bitumen, etc);
(d) constructed generally in accordance with Planning Scheme Policy No. 9 “Waste
Management Multi-Dwellings and Commercial and Industrial Premises’.
11. A bin washdown pit lawfully directed to the effluent disposal must be provided for the
cleansing of all refuse bins. This may be a separate area or form part of the storage area
required in the above condition. Where this area is separate and is not roofed, the
stormwater catchment area must comply with plumbing and drainage requirements.
12. A Waste Management Plan (WMP) must be developed and implemented on site. This plan
shall:
(a) appoint the site management entity as responsible for administering the plan;
(b) require that all waste materials be segregated into general and recyclate waste
streams and stored within their appropriate refuse bin within the storage area;
(c) outline refuse obligations of patrons that stay on site,
(d) appoint person(s) responsible for the transportation of refuse containers from the
storage area to an approved Council refuse facility,
(e) appoint the person(s) responsible for cleaning bins on-site and maintaining the
storage area and litter bins in a clean and tidy state; and
FM1404/9-01/10/2013 Page 10
Page 57 of 231See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.