PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 25 MARCH 2014
Page 58 of 231
PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 25 MARCH 2014
(f) where required, ensure the use of on-site litter bins for patrons,
(g) require the removal of all waste off site on a minimum weekly basis,
(h) require that all waste materials are adequately secured and covered when being
transported off site to the approved disposal facility.
13. Refuse obligations for patrons outlined in the WMP shall be included as part of a site
operational plan.
Acoustics
14. For noise from amplified music and entertainment between the hours of 7:00am and
10:00pm, the adjusted maximum sound pressure level Lajo, plus adjustments for tonal and
impulse components, must not exceed the background level Lago by more than 5 dB(A)
when measured at any affected premises.
15. Noise from amplified music and entertainment must not be audible at any affected
premises between the hours of 10:00pm and 7:00am.
16. Where a complaint (other than a frivolous or vexatious complaint) is made to Council about
noise from the premises, the following shall be provided to Council, when requested:
(a) have a suitably qualified acoustic consultant undertake a Noise Impact Assessment
(NIA) in accordance with relevant guidelines and standards, and have a report
submitted to Council for endorsement which outlines the findings of the NIA; and/or
(b) the installation of volume limiting devices and/or upgrade the sound reduction index
(R) value of windows, doors and/or shield mechanical plant and equipment, and/or
provide internal frequency absorptive or sound proofing treatments within the site,
and/or install acoustic barriers to mitigate or reduce noise impacts and have any
such upgrades or works certified by a suitably qualified acoustic consultant;
17. Service vessel movements associated with the approved use (including loading and
unloading and transport of patrons) for the use of the Registered Barge, must not occur
outside the hours of 7am to 10pm Monday to Sundays. The requirements of this condition
must be included into any accommodation agreement or equivalent operational plan.
ENGINEERING UNIT
Stormwater Drainage
18. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site.
Damage to Services and Assets
19. Any damage caused to existing services and assets above or below the ground must be
repaired:
(a) where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
(b) where otherwise, upon completion of the works associated with the development.
(c) Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
FM1404/9-01/10/2013 Page 11
Page 58 of 231See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.