SUPERSEDED - Decision Notice MCU22/0082 OPW22/0134 [As Published]
SITE SPECIFIC CONDITIONS
35. A loading and unloading zone suitable for a single AV Tractor Trailer must be line-marked in
accordance with relevant Australian standards. The loading and unloading zone must be
located opposite the proposed staff carparks as to not limit the functionality of the carpark.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
36. All necessary approvals from external service providers (e.g. Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
37. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
38. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
39. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
Erosion and sediment control works;
b. Other relevant parties
40. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
41. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
42. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
43. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
Page 6 of 14
Document Set ID: 22208842
Version: 4, Version Date: 14/12/2022