RFI (rec. 5.06.26) 2567 - Appendix C - Waste Management Plan (WMP) (Ver. 2)
Original PDF page 10, section 1. The text section number identifies this passage in the reader.
3.3 General Waste
The Waste Management Planning Scheme Policy does not specify minimum general waste
service levels for low impact industrial development. General waste volumes have therefore
been calculated using a consistent industry-standard waste generation rate applied across
all stages of development. General waste volumes generated by the development are
broken down as per Table 3.
Table 3 - General Waste Bin Calculations
Stage General Waste
Generation Adopted No. of 2m³
No. of 2m³ Bins
(m³/week) Bins
Stage 1 2.1 1.1 1
Stage 2 2.6 1.3 1
Stage 3 1.3 0.7 1
Stage 4 3.0 1.5 2
Stage 5 1.6 0.8 1
All Stages Total 10.7 5.4 6
The total amount of bins needed to accommodate the general waste generated by the low
impact industrial uses across all stages is 6 (six) 2 cubic litre bins per week.
2576-WMP-01 v2 (April 2026) Page 7 of 16
EA/TB