Skip to the record
The only place to find full transcripts.

Original source · versioned page text

Reference Document - MCU24/0002 [As Published]

of 43

Page text shows just the words. Original shows the document exactly as it was published.

Original PDF page 9, section 1. The text section number identifies this passage in the reader.

                                                                                                         Job No: 23-458
                                                                                                                 Page 9

                  2.5.3 Type of Fill
                  Site won or imported fill must be placed in accordance with AS3798-2007. Imported select fill material
                  should be a good quality select fill material with a soaked CBR of at least 10%, a maximum aggregate
                  size of 50mm, and a maximum Shrink/Swell Index of 1.0%. Fill must be keyed into the existing slopes.
                  2.5.4 Stormwater Disposal
                  Stormwater collected within the site should be directed into designated drains and directed to Council's
                  stormwater system. Disposal of stormwater on the surface is not permitted in the immediate vicinity of
                  the proposed building area;
                  2.5.5 Site Drainage
                  Surface run-off should be diverted away from the proposed retaining walls and dwelling to prevent
                  scouring, riling, and erosion. Drains should be lined to prevent water from entering behind the wall. The
                  site drain shall be designed and inspected by a qualified person.
                  2.5.6 Footing System
                  All footings must be designed in accordance with AS2870-2011. It is understood that piers and pier
                  supported slab on-ground footing systems are proposed for the site. This type of footing system is
                  considered appropriate for the site. However, the piers must be extended beyond any fill and sufficiently
                  socketed into extremely weathered rock or better materials. Under no circumstances should the piers
                  be terminated within fill.
                  The proposed swimming pool located downslope within the site should also be supported on piers that
                  are socketed into the basement rock.
                  2.5.7 Roof Water Control
                  It is understood that rainwater tanks would be used on site. Ensure overflow and other downspouts are
                  not flowing onto any fill/slopes but are collected and channelled into storm water drains. Leaks along
                  these lines should be avoided.
                  2.5.8 Erosion Control
                  Erosion protection of all exposed batters should be carried out at the site. All run-off at the site should
                  be appropriately channelled to ensure that run-off does not cause severe erosion that may result in
                  adverse ground profiles.

                  2.5.9 Retaining Walls
                  All proposed retaining structures should be designed by a qualified engineer and checked for global
                  stability, sliding, and rotational failure.

                  2.5.10 Wastewater and Sewerage System
                  Qualtest is unaware of the sewerage system planned for the site. However, to not adversely affect the
                  performance of the site slopes, wastewater land application area should be located at least 10m
                  downslope of the proposed residence.
                  Following the implementation of the above recommendations, the site has been reassessed, based on
                  Cases 1 – 22, to have a hazard rating of 0.46, corresponding to a “Low" landslide risk.

                  3.0 CONCLUSION

                  To progress the proposed development at #399 Sunrise Road, Tinbeerwah, Council requested a report
                  on the stability of the site, which has been identified as being within the map overlay for landslide hazard.

                  The slope stability (landslide) assessment has been conducted, and the site, in its current state, has
                  been assigned a "Moderate" landslide risk category. Following the implementation of the
                  recommendations in Section 2.5, the risk of landslide events has been revised to “Low”.

                  Based on our site inspection and sub-surface analysis, we conclude that the site is suitable for the
                  proposed development and has a “Low" risk to slope instability, provided the recommendations outlined
                  in this report are adhered to.




                                                                                                                  Ref: 4602
                                                                                             399 Sunrise Road, Tinbeerwah
Document Set ID: 22750694
Version: 1, Version Date: 03/01/2024
Log in to download the original file

Reference Document - MCU24_0002 [As Published].pdf · 9.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.