Geotech Report - Initial Findings
Attached to the e-mail Operation Works Application - OPW19/0266 - 215 David Low Way, Peregian Beach - (EMAIL 2/3) - Site Based Stormwater Management Plan, Acid Sulphate Soil & Groundwater Management Plan.
Essence of Peregian
215-219 David Low Way, Peregian Beach
Project No. 007-160A,
27 April 2010
SECTION 1 - INTRODUCTION
1.1 Project
It is understood that it is proposed to develop the site by the construction of a residential and commercial
development comprising multiple two and three storey buildings, access roads, driveways and car parking
areas. It is also understood that excavations of up to approximately 3m will be required in the eastern part of
the site to form partially in-ground basement car parking and that approximately 1m of fill is to be placed over
the western part of the site. The location of the site and the layout of the proposed development are shown
approximately on Drawing No. 1, attached.
1.2 Proposed Scope of Work
Based on prior experience at the site, the subsurface conditions were generally anticipated to comprise a
discontinuous surface layer of fill, underlain by predominantly sandy alluvial strata (including indurated sand
layers) overlying residual soils then weathered rock (generally at increasing depth from east to west). It was
proposed to undertake additional geotechnical investigation of the site by drilling and sampling six bores to
6m to 7m depth.
Using the results of relevant existing investigation information and the fieldwork outcomes obtained from the
proposed additional investigation, it was proposed that a report would be produced that would provide
geotechnical design information on each of the following topics:
subsurface conditions; working bearing pressures;
earthworks and site preparation; estimated site settlement;
reactive soil movement; anticipated founding depths; and,
retaining wall pressures; anticipated construction aspects.
suitable alternate foundation types;
1.3 Commission
A fee to undertake the investigation was presented in a proposal of 12 March 2010 and
Butler Partners Pty Ltd was subsequently commissioned by Scanlon Property Group Pty Ltd to conduct the
geotechnical investigation as proposed.
butlerpartners.com.au Page 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.