Negotiated Decision Notice OPW26 0033 (As Published)
39. A hold point inspection is required with a Council delegate upon completion of the following
stages of road construction:
a. subgrade; and
b. base course (pre-seal).
At the time of the inspection(s), the pavement layer must exhibit no visible signs of
deformation under proof rolling by a fully loaded water truck to the reasonable satisfaction of
Council. The pavement layer will not pass the inspection until this requirement has been
achieved.
(*) Refer to Advisory Note
40. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
41. Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
42. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
43. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Pathways
44. All pathways must be constructed in accordance with the following requirements:
a. all footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065;
b. provision must be made for disabled access at all kerb crossings associated with
pathways, in accordance with Council's current standards;
c. all paths must have a slip resistant surface;
d. expansion and contraction joints must provide a flush finish. Installation of joints by saw
cutting is preferred to ensure a smooth ride for cyclists; and
e. the required work includes any modifications to ensure the footpath finishes flush with
all existing service covers and the like, or alternatively these services are raised or
altered, so as not to create a pedestrian safety hazard.
45. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety; and
b. be designed and constructed to comply with the Disability Discrimination Act (DDA),
Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
access and mobility.
Page 12 of 22
Document Set ID: 25209919
Version: 4, Version Date: 02/10/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Negotiated Decision Notice OPW26 0033 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.