Negotiated Decision Notice OPW26 0033 (As Published)
SITE SPECIFIC CONDITIONS
Erosion and Sediment Control Plans
3. Submit a site-specific Erosion and Sediment Control Plan in accordance with the
International Erosion Control Association’s (IECA) Best Practice Erosion and Sediment
Control and prepared by a suitably qualified person (RPEQ and/or CPESC). The Plan must
be submitted prior to the commencement of works.
4. Prior to the commencement of bulk earthworks:
a. a hold-point inspection is required with a Council delegate to review that the erosion
and sediment controls on-site generally reflect the Erosion and Sediment Control Plan.
b. certification from a suitably qualified person (RPEQ and/or CPESC) must be submitted
to Council certifying that the erosion and sediment controls on site have been installed
in accordance with the Plan and IECA’s Best Practice Erosion and Sediment Control.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
5. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. civil engineering works;
b. arboreal (tree) works;
c. fauna management works;
d. landscape works;
e. rehabilitation works;
f. erosion and sediment control works; and
g. other relevant parties.
6. Prior to requesting a prestart meeting:
a. Tree protection fencing must be installed under the supervision of the qualified person*.
(Refer to Retention of Existing Trees conditions).
b. Pre-clearance surveys and habitat assessment required by the approved Fauna
Management Plan and conditions of this Decision Notice, must be undertaken (Refer
to Fauna Management conditions).
7. Submit a copy of the approved plans that are issued “For Construction” and duly signed by
the consultant Registered Professional Engineer of Queensland (RPEQ). Plans must be
submitted and approved by Council prior to the pre-start meeting.
8. Submit certificates demonstrating currency of public liability insurance and works insurance
covering the works. Certificates must be submitted to Council prior to the pre-start meeting.
9. Submit a condition report documenting any existing defects in the road reserve or
infrastructure, including photographs of the site frontage. The report must be submitted to
Council prior to the pre-start meeting.
Page 4 of 22
Document Set ID: 25209919
Version: 4, Version Date: 02/10/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Negotiated Decision Notice OPW26 0033 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.