                                                                                Officer:            Matthew Pinese
                                                                                Direct Telephone:   07 53296316
                                                                                Our Reference:      51989.294.03
                                                                                Your Reference:     n/a

               18 May 2026


               KLV Brinkley
               C/- Brennan Planning Pty Ltd
               44 Maple St
               COOROY QLD 4563


               [email protected]



               Dear Marcus,
                                            Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 25 March 2026, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              51989.294.03

                   Street address:              Retreat Peregian 3/390 David Low Way Peregian Beach Qld 4573

                   Real property description:   Lot 3 GTP 102586 and GTP 102586

                   Planning Scheme:             Noosa Plan 2020 (20 March 2026)

               2.      DECISION DETAILS

               The following type of approval was issued on 1 June 1989
               •       Development Permit for Material Change of Use of Premises – Group Housing
                       Development of 21 Dwellings
               In relation to the request to make a minor change to the existing approval, Council on 15 May 2026,
               decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change.
               B.      Include additional conditions 32 to 45
               C.      Undertake minor administrative amendments to condition 31 approved plans table to rectify
                       incorrect dates and revision number.




               ABN 97.969.214.121                                                              PO Box 141
               noosa.qld.gov.au                                                         Tewantin QLD 4565
               [email protected]                                                         07 5329 6500
                                                                                                         Page 1 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026
Full text of the other 8 pages

Page 2

               3.     CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.     ASSESSMENT MANAGER CONDITIONS

               1.     Payment of contributions in accordance with Council's Policy on Water Supply and Sewerage
                      Headworks, current at the time of Building approval. Calculations based upon the current
                      Policy including Price Index variation as at April, 1989, for water supply are estimated at
                      $3,175/dwelling house. If payment is not proposed to be made prior to the issue of Building
                      Approval, a cash bond or trading bank guarantee for the required amount is to be lodged
                      prior to the release of that Approval. The contribution is then required to be made within
                      fourteen (14) days of the issue of Building Approval.
               2.     Construction of roadworks, including access to the site, drainage and footpath improvements
                      across the full frontage of the development to connect to existing construction to the south
                      of the subject site, to the satisfaction of the Main Roads Department and Council's Shire
                      Engineer. Such works shall involve the construction of kerb and channel, bitumen widening,
                      associated drainage, hot mix correction to the existing pavement, and footpath upgrading
                      works. In this regard, plans prepared by a registered Civil Engineer are to be submitted to
                      and approved by the Shire Engineer and the Main Roads Department prior to the issue of a
                      Building Approval.
                      The Engineering design is to specifically include details of available sight distance at the
                      proposed access location, cross sections at 25 m. intervals, and the extent of proposed
                      clearing works to enable roadworks/retaining wall construction and the relation of these
                      works with respect to existing properties. The Applicant is to note that the proposed “Access
                      Only” to David Low Highway is not approved and ingress/egress is to be from a single
                      location only. The internal driveway is to be amended to provide a minimum 4.5 metre wide
                      driveway for 2-way operations with a three point turning area to be provided at the termination
                      of the driveway. Consideration may be given to reducing the required driveway width to 3.0
                      m. provided passing bays are appropriately located. All earthworks and retaining structures
                      associated with the driveway construction are to be contained entirely within the subject site.
               3.     The footpath to the frontage of the site is to be upgraded to the satisfaction of the Shire
                      Engineer.
               4.     The provision of any structural retaining works required to facilitate compliance with
                      Conditions 2 and 3 shall be effected at the developer's expense. An Engineering design of
                      the proposed structures, together with a landscaping plan relating to the retaining structures,
                      are to be submitted for approval by the Shire Engineer prior to issue of a Building Approval.
                      Such works shall be designed and constructed with a view to minimising damage to existing
                      vegetation in the road reserve.
               5.     The developer shall bear the cost of alteration of any public utility or facilities necessitated
                      by the development of the land or associated construction works external to the site.
               6.     Connection to Council's existing water supply reticulation system and the provision of internal
                      reticulation at the developer's expense to the standards and requirements of Council's Shire
                      Engineer. The internal reticulation shall be constructed and maintained by the owner.
               7.     The development will provide for the disposal of all sewerage and sullage wastes resulting
                      from the occupation of the proposed building by constructing and installing a package
                      treatment plant and associated absorption trenches and replacement fields at cost to the
                      developer and to the standards required by the Shire Engineer. Consideration will be given
                      to irrigation of the effluent within the landscaped areas of the site provided that the Applicant's
                      Engineer can demonstrate to the satisfaction of the Shire Engineer that adequate area is
                      available, having regard to the expected maximum population on the site.




                                                                                                           Page 2 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 3

                      The design of the proposed effluent disposal system is to:—
                      a.      be prepared by a registered civil engineer engaged by the applicants,
                      b.      be approved by Council’s engineer prior to the issue of a Building Approval.
               8.     The Applicants will arrange for the construction and installation of the said package treatment
                      plant and absorption field (or irrigation system subject to the Shire Engineer’s approval) to
                      be supervised by a registered civil engineer. On completion of the work, the developer’s
                      engineer shall certify that the system has been installed as approved by the Council’s
                      Engineer.
               9.     The Applicant’s civil engineer shall design the said package treatment plant so as to ensure
                      that it is accessible by vehicle for both maintenance and sludge removal. An area is also to
                      be provided for the storage of chemicals and equipment and provision is to be made for
                      cleansing this area and such equipment employed. The detailed design necessary to comply
                      with this requirement is to be submitted to and approved by the Council’s Engineer prior to
                      the issue of a Building Permit.
               10.    The Applicants are to be responsible for ensuring the proper and effective maintenance of
                      the package treatment plant and absorption trench field. Prior to the occupation of the
                      buildings, the Applicants will:—
                      a.      Enter into a permanent maintenance contract with the manufacture of the package
                              plant and proof of this contract shown to the Shire Engineer.
                      b.       Enter into a legally binding agreement with the Council whereby the Council’s officers,
                              servants or agents shall at all times be at liberty to enter upon the subject land with or
                              without vehicles, plant and equipment for the purpose of inspecting the package
                              treatment plant and absorption field.
                      c.      Enter into a legally binding agreement with the Council whereby the Council shall be
                              paid for every inspection as is reasonably required in accordance with the Council’s
                              duties at the rate of $50.00 per inspection (or other amount as determined by Council
                              resolution); such agreement to provide that such inspection fee shall be paid quarterly
                              and increase correspondingly with the annual percentage increase in the Consumer
                              Price Index from the date of this approval.
               11.    The Applicants will construct an underground drainage system designed to the requirements
                      and standards of the Council’s Engineer so as to dispose of all stormwater runoff which falls
                      upon the subject land or is naturally concentrated upon it. All stormwater must be collected
                      upon the subject land and connected into the system. Such drainage system shall extend
                      from the subject land to the existing natural creek to the north where a dissipator type outlet
                      also approved by the Council’s Engineer shall be provided by the Applicants at the proposed
                      outfall to the creek. The Applicant’s knowledge that the prior approval of the Land
                      Administration Commission shall be necessary before the Council’s Engineer can finally
                      approve this method of disposal. The Applicants will submit the necessary documentation
                      from the abovementioned drainage system to the Council prior to the issue of a building
                      permit and a building permit will not be issued until the documentation has been approved
                      by the Council’s Engineer.
               12.    The proposed beach accesses are to be of board and chain construction with the locations
                      and construction principles approved by the Beach Protection Authority prior to works
                      commencing. The access at the north of the site shall connect into the existing informal beach
                      accesses through the Council reserve. The existing accesses from this point to the beach
                      shall be upgraded to the standards and requirements of the Beach Protection Authority and
                      Council.
               13.    Submission to and approval by Council of building plans in accordance with the Building Act,
                      Council’s By-laws and Policies, and generally in accordance with the plan approved in this
                      Consent and the Shire of Noosa Town Planning Scheme apart from where amendments are
                      required or dispensations have been granted in conjunction with this Consent.



                                                                                                          Page 3 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 4

               14.    Provision of at least 27 off-street car parking spaces, comprising 21 covered spaces and 6
                      uncovered spaces, and access thereto which are to be provided with a sealed pavement and
                      designed, drained, constructed and maintained in accordance with the Town Planning
                      Scheme, Council’s Policies and to the reasonable satisfaction of the Shire Engineer. Plans
                      and specifications for these works are to be submitted to the Shire Engineer for approval in
                      conjunction with the Building Application.
               15.    There is to be no detrimental effect upon the amenity of the neighbourhood by reason of the
                      creation of excessive noise, lighting nuisance or other emissions.
               16.    The open space and setback areas are to be landscaped in accordance with the Noosa
                      Design Manual and a properly prepared landscaping plan to be submitted to and approved
                      by the Shire Planner, prior to the issue of a Building Approval. Such landscaping is to be
                      completed in accordance with the approved landscaping plan prior to the premises being
                      occupied and maintained at all times thereafter to the reasonable satisfaction of the Shire
                      Planner.
               17.    Existing trees are to be retained, except where required to be removed due to building
                      operations or the conduct of the approved use.
               18.    Construction work is permitted only during the hours of 7.00 a.m. to 6.00 p.m. Monday to
                      Saturday and no construction work is permitted on public holidays, except where extended
                      hours are approved by the Building Surveyor.
               19.    Any advertising sign or device is to comply with the provisions of the Noosa Design Manual.
               20.    The developer shall bear the cost of alteration of any public utility or facilities necessitated
                      by the development of the land or associated construction works external to the site.
               21.    Provision of approved refuse containers in accordance with the requirements of the Refuse
                      Management Regulations of 1983 for the storage and collection of refuse to the satisfaction
                      of Council’s Health Surveyor.
               22.    Any flat or unit intended to be let out for fee or reward is to be licensed annually with Council’s
                      Health Department in accordance with the provisions of Chapter 43 of Council’s By-Laws
                      prior to such letting.
               23.    The swimming pool shall be licensed annually with the Council’s Health Department in
                      accordance with the provisions of Chapter 42 of Council’s By-Laws.
               24.    Submission of a cash bond or trading bank guarantee to the sum of $20,000 to secure
                      performance of conditions, prior to the issue of Building Approval. The cash bond or trading
                      bank guarantee may be returned to the developer upon performance of the conditions of
                      approval.
               25.    The provisions of this Town Planning Consent are to be effected prior to the commencement
                      of the specific use granted under this Consent. Council reserves the right to call upon the
                      bond or guaranteed sum referred to in this approval for the purposes of litigation should the
                      use not be conducted in accordance with this Approval.
               26.    This Consent may be revoked pursuant to Section 33 (16D) of the Local Government Act if
                      substantial progress has not been made in the erection of any building or other structures in
                      accordance with this Consent or the rights conferred by this Consent are not exercised in
                      accordance with this Consent within two (2) years of the date thereof.
               27.    The tennis court shall remain unlit.
               28.    The beach front building setback may be reduced to 1.5 metres.
               29.    The minimum setback from the David Low Highway shall be 6.0 metres.
               30.    Payment of outstanding fees of $130 prior to the issue of a Building Permit.




                                                                                                           Page 4 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 5

               31.    Additional Conditional - Approved Plans 14 September 2022 – Unit 2

                        Plan No.          Rev.   Plan/Document Name                             Date

                        SK_3.01           D      Site Plan, prepared         by     Blackwood 22/06/2022
                                                 Architecture & Design

                        SK_4.3            D      Proposed Basement Plan, prepared by 22/06/2022
                                                 Blackwood Architecture & Design

                        SK_4.4            D      Proposed Ground Floor Plan, prepared by 22/06/2022
                                                 Blackwood Architecture & Design

                        SK_4.5            D      Proposed Level 1, prepared by Blackwood 22/06/2022
                                                 Architecture & Design

                        SK_5.5            D      Proposed North Elevation, prepared by 22/06/2022
                                                 Blackwood Architecture & Design

                        SK_5.6            D      Proposed East Elevation, prepared by 22/06/2022
                                                 Blackwood Architecture & Design

                        SK_5.7            D      Proposed South Elevation, prepared by 22/06/2022
                                                 Blackwood Architecture & Design

                        SK_5.8            D      Proposed West Elevation, prepared by 22/06/2022
                                                 Blackwood Architecture & Design

               32.    Additional Condition – 15 May 2026 – Unit 3
                      Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                        Plan No.          Rev.   Plan/Document Name                             Date

                        202618/DA1.08     A      Demo Basement       Plan,    prepared       by 2/03/2026
                                                 Blackwood

                        202618/DA1.09     A      Demo Ground Floor Plan, prepared by 2/03/2026
                                                 Blackwood

                        202618/DA1.10     A      Demo Level     01   Plan,        prepared   by 2/03/2026
                                                 Blackwood

                        202618/DA2.01     A      Proposed Basement Plan, prepared by 2/03/2026
                                                 Blackwood

                        202618/DA2.02     A      Proposed Ground Floor Plan, prepared by 2/03/2026
                                                 Blackwood

                        202618/DA2.03     A      Proposed Level 1 Plan, prepared by 2/03/2026
                                                 Blackwood

                        202618/DA2.04     A      Proposed Roof       Plan,    prepared       by 2/03/2026
                                                 Blackwood




                                                                                                       Page 5 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 6

                        202618/DA3.07       A      North Elevation Proposed, prepared by 2/03/2026
                                                   Blackwood

                        202618/DA3.08       A      East Elevation Proposed, prepared by 2/03/2026
                                                   Blackwood

                        202618/DA3.09       A      South Elevation Proposed, prepared by 2/03/2026
                                                   Blackwood

                        202618/DA3.10       A      West Elevation Proposed, prepared by 2/03/2026
                                                   Blackwood

                        202618/DA3.11       A      Section A       Proposed,    prepared     by 2/03/2026
                                                   Blackwood

                        202618/DA3.12       A      Section B       Proposed,    prepared     by 2/03/2026
                                                   Blackwood

                        202618/DA3.13       A      Section C, prepared by Blackwood               2/03/2026

                        202618/DA6.01       A      Powdery Room Joinery Plan, prepared by 20/03/2026
                                                   Blackwood

               Partial Demolition of Existing Building
                      Codes of Development
               33.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               34.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               35.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               36.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               37.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work.
                      Water Quality and Drainage
               38.    Erosion and sediment control is to be undertaken in accordance with the requirements of the
                      Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
                      maintained until soils are stabilised by vegetation or sealed.
                      NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
                      allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
                      system (e.g. roadside gutter).




                                                                                                       Page 6 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 7

                      Health and Safety
               39.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               40.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.
               41.    Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
                      requires a licensed asbestos removalist to give notice to Workplace Health and Safety
                      Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
                      commences. Notification must be made using Form 65: Notification of licensed asbestos
                      removal work, demolition work or emergency demolition.
               42.    All building materials containing asbestos products are wrapped and disposed of in
                      accordance with the Public Health Regulation 2006 and the Environmental Protection
                      Regulation 2008.
                      Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
                      businesses that transport asbestos waste, and landfills that accept this waste.
                      General
               43.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.
               44.    Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
                      bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
                      pre-existing conditions.
                      Plumbing and Drainage
               45.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further information, please refer to Infrastructure Charges | Noosa Shire Council
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.




                                                                                                       Page 7 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 8

               9.       FURTHER DEVELOPMENT PERMITS REQUIRED

                   Type of Development Permit Required                            Subject of the required Development Permit

                   Development Permit for Building Works                          All building work.

               10.      SUBMISSIONS

               Not applicable.
               11.      RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               12.      OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.

               Yours faithfully



               Matthew Pinese
               Development Planner | Development Assessment
               Development & Regulation



               Enc:     Appeal Rights
                        Approved Plans/Documents




               DECISION NOTICE HISTORY
               •     Original Decision Notice – 1 June 1989.

               •     Decision Notice - Minor - 51989.294.01 – 13 June 2018; Generally in accordance

               •     Decision Notice – Minor – 51989.294.02 – 14 September 2022; additional condition 31 (Unit 2).
               •     Decision Notice - Minor – 51989.294.03 – 15 May 2026 with an administrative amendment to condition 31 and additional conditions
                     32-45.




                                                                                                                                    Page 8 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Page 9

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 9 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Used in these records

About this file

File size
170 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51989 294 03 (As Published).pdf · 170 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.