               3.     CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.     ASSESSMENT MANAGER CONDITIONS

               1.     Payment of contributions in accordance with Council's Policy on Water Supply and Sewerage
                      Headworks, current at the time of Building approval. Calculations based upon the current
                      Policy including Price Index variation as at April, 1989, for water supply are estimated at
                      $3,175/dwelling house. If payment is not proposed to be made prior to the issue of Building
                      Approval, a cash bond or trading bank guarantee for the required amount is to be lodged
                      prior to the release of that Approval. The contribution is then required to be made within
                      fourteen (14) days of the issue of Building Approval.
               2.     Construction of roadworks, including access to the site, drainage and footpath improvements
                      across the full frontage of the development to connect to existing construction to the south
                      of the subject site, to the satisfaction of the Main Roads Department and Council's Shire
                      Engineer. Such works shall involve the construction of kerb and channel, bitumen widening,
                      associated drainage, hot mix correction to the existing pavement, and footpath upgrading
                      works. In this regard, plans prepared by a registered Civil Engineer are to be submitted to
                      and approved by the Shire Engineer and the Main Roads Department prior to the issue of a
                      Building Approval.
                      The Engineering design is to specifically include details of available sight distance at the
                      proposed access location, cross sections at 25 m. intervals, and the extent of proposed
                      clearing works to enable roadworks/retaining wall construction and the relation of these
                      works with respect to existing properties. The Applicant is to note that the proposed “Access
                      Only” to David Low Highway is not approved and ingress/egress is to be from a single
                      location only. The internal driveway is to be amended to provide a minimum 4.5 metre wide
                      driveway for 2-way operations with a three point turning area to be provided at the termination
                      of the driveway. Consideration may be given to reducing the required driveway width to 3.0
                      m. provided passing bays are appropriately located. All earthworks and retaining structures
                      associated with the driveway construction are to be contained entirely within the subject site.
               3.     The footpath to the frontage of the site is to be upgraded to the satisfaction of the Shire
                      Engineer.
               4.     The provision of any structural retaining works required to facilitate compliance with
                      Conditions 2 and 3 shall be effected at the developer's expense. An Engineering design of
                      the proposed structures, together with a landscaping plan relating to the retaining structures,
                      are to be submitted for approval by the Shire Engineer prior to issue of a Building Approval.
                      Such works shall be designed and constructed with a view to minimising damage to existing
                      vegetation in the road reserve.
               5.     The developer shall bear the cost of alteration of any public utility or facilities necessitated
                      by the development of the land or associated construction works external to the site.
               6.     Connection to Council's existing water supply reticulation system and the provision of internal
                      reticulation at the developer's expense to the standards and requirements of Council's Shire
                      Engineer. The internal reticulation shall be constructed and maintained by the owner.
               7.     The development will provide for the disposal of all sewerage and sullage wastes resulting
                      from the occupation of the proposed building by constructing and installing a package
                      treatment plant and associated absorption trenches and replacement fields at cost to the
                      developer and to the standards required by the Shire Engineer. Consideration will be given
                      to irrigation of the effluent within the landscaped areas of the site provided that the Applicant's
                      Engineer can demonstrate to the satisfaction of the Shire Engineer that adequate area is
                      available, having regard to the expected maximum population on the site.




                                                                                                           Page 2 of 9
Document Set ID: 24800867
Version: 4, Version Date: 25/05/2026

Used in these records

About this file

File size
170 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51989 294 03 (As Published).pdf · 170 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.