                                           PROPOSED SUBDIVISION
                                           41 TALLOWWOOD PLACE, BLACK MOUNTAIN

            The proposed new development area is located on a moderately sloping, relatively linear and planar shaped
            part of the ridge flank, with gradients typically in the order of about 15° to 17°, steepening downslope up to
            about 20°.
            To the south of the proposed new building area, the ground surface had been altered by previous cut and fill
            earthworks presumably during the construction of Tallowwood Place. The roadside fill embankments were
            estimated to range up to about 1.5 m high, and were typically battered between 30° and 35°; however,
            crestline slumping was observed in parts resulting in steeper sections. An apparent track was observed
            cutting across the roadside fill embankment down to the proposed new building area. It appeared that cut/fill
            earthworks less than 1 m depth/height had been undertaken to form the track; however, due to the long
            grass visual appraisal was difficult.



                Apparent Track




                                                                                      Rock Fill Embankment




            Text Figure 6: Views of roadside fill embankments

            A drainage line intersected the ridge flanks between the existing residence and proposed new building area.
            The roadside embankment across the head of this drainage line comprised imported rock fill, being about
            3 m high, and battered between about 25° and 30°. Rock spalls extended from the toe of the rock fill batter
            to the southern property boundary, with a level track about 5 m wide traversing the head of the drainage line.
            It was estimated that about 2 m of fill had been placed over the drainage line.

            Based on the above observations, it appeared that a section of Tallowwood Place about 40 m to the south-
            west of the existing residence had been impacted by a previous landslide. It appears that the area was
            remediated using rock fill; however, no design details were available. A review of higher resolution aerial
            imagery from Nearmap and Qimagery suggests that the rock fill embankment has been in place since 2006;
            however, due to the low resolution of earlier images it cannot be confirmed prior to this.

            A stormwater pit was observed at the crest of the rock fill embankment; however, there was no obvious
            evidence of an outlet below the toe of the batter. Text Figures 7 and 8 overleaf illustrate this area at the time
            of the investigation.




             22 May 2023
             Report No. 23099-001-Rev0                              5

Document Set ID: 22826802
Version: 1, Version Date: 23/02/2024
Log in to download the original file

Reference Documents.pdf · 13.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.