PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the Ordinary Meeting dated 19 March 2026 - Item 12.2) · 2026-06-09 ATTACHMENT 1 to Minutes of General Committee 9.06.2026 - Peregian Beach Active Street - Further Information

of 8

Page text shows just the words. Original shows the document exactly as it was published.

ATTACHMENT 1 to the Minutes of the General Committee Meeting dated 9 June 2026
- Peregian Beach Active Street - Stage 1 Progress Update and Next Steps Report –
Further information

FURTHER INFORMATION

Author            Project Officer, Lindsay Egeskov,
                  Major Projects & Transport | Infrastructure Services Department



Background and Strategic Foundations
‘THE NOOSA CYCLING AND WALKING STRATEGY AND IMPLEMENTATION PLAN
(NCWSIP)’]
Noosa Liveability Survey
The project reflects community feedback from the 2022 Noosa Liveability Survey, where residents
called for safer routes, better transport options and improved connectivity. These priorities are
reiterated in the most recent Noosa Liveability Survey (2026), clearly demonstrating that community
needs remain consistent and underscoring the ongoing relevance of the project. The highest-priority
themes identified across the shire are illustrated in figure 2 below and include 'walking/jogging/bike
paths that connect housing to communal amenity' and 'Access and safety of walking, cycling and/or
public transport'.




Figure 2 - Noosa Liveability: Strengths and Priorities


Program
The project program is governed by Council's Annual Capital Works Programs and two separate
external funding agreements as outlined below. Following the March Ordinary Meeting and the
decision to defer the report until June, extension of time requests were submitted to each funding
body as a mitigation measure to address risks to the project program. Council has successfully
secured approval for the extension of time requests with both the Active Transport Fund, and the
SEQ Liveability Fund. The revised milestone dates are outlined below.


                                                                                          1|Page
Log in to download the original file

2026-06-09 ATTACHMENT 1 to Minutes of General Committee 9.06.2026 - Peregian Beach Active Street - Further Information.pdf · 659 KB (small file)

Full text of the other 7 pages

Page 2

SEQ Liveability
The last possible dates for milestones as listed in the executed SEQ Liveability funding agreement,
are:
Milestone                 Last Possible Date (as                               Status
                                                 Current Approved
                          per Program
                                                 Variation Date
                          Guidelines)
Completion of             30 Jun 2027                                          Achievable
                                                     31 Dec 2027
Construction
Final Reporting           31 Dec 2027                30 June 2028              Achievable


Active Transport Fund
The last possible dates for milestones as listed in the executed ATF funding agreement, is:
Milestone                 Last Possible Date (as                               Status
                                                 Current Approved
                          per Program
                                                 Variation Date
                          Guidelines)
Commencement of           25 Mar 2026                                          Achievable
                                                    20 Oct 2026
Construction
Completion of             25 Mar 2028                                          Achievable
                                                    NIL
Construction
Acceptance of          25 Jun 2028                                             Achievable
                                                    NIL
Post-Completion Report


Current Project Program
The current program is based on receiving Council support by no later than the June Ordinary
Meeting. Construction is anticipated to begin in October 2026 with practical completion being
achieved in December 2027. The full program, including additional project consultation activities
contributing to the extension of time required is provided at attachment 8. Further delays would put
the project at significant risk, as the maximum allowable extension of time request from SEQ
Liveability has already been sought, and the chance of receiving a second extension of time past
this deadline is highly unlikely. It would also put Councils reputation with grant funding bodies at risk,
compromising future grant opportunities.
Table 1 below indicates current forecast milestone dates as per the project program.
Milestones                                   Deadline
Council Decision - General Committee         9 June 2026
IFC Design                                   13 July 2026
Award Tender                                 17 Sep 2026
Practical Completion                         6 Dec 2027
Handover – final report & funding acquittal30 June 2028
Table 1: Program Milestones




                                                                                              2|Page

Page 3

Design changes arising from Community Engagement
Lorikeet Park Boardwalk
The originally approved scope of works south of the Lorikeet Drive cul-de-sac included the
replacement of a timber boardwalk over existing culverts with a concrete footpath, as well as the
construction of an upgraded footpath south of the boardwalk on a revised alignment within Council
managed road reserve.
Subsequent community engagement has highlighted a preference to retain the timber aesthetic of
the boardwalk and to maintain the existing footpath alignment south of the boardwalk. Further
investigations have indicated that the existing concrete box culverts are in poor condition and are
unsuitable for the proposed boardwalk/pathway works to proceed without repairs/replacement. In
addition, community CPTED concerns with the proposed pathway alignment, and land tenure
constraints affecting the existing pathway alignment have necessitated further investigation, which
would benefit from additional time and resourcing.
Allowing for this additional timeframe will also enable greater clarity regarding the design of the
connecting Sunshine Coast Council pathway at the Emu Mountain Road roundabout, ensuring a
seamless transition between the two local government areas.
In light of these considerations, the project team recommends postponing this scope to a future
project stage to allow for more comprehensive planning of the proposed changes and better
alignment with community expectations.


Risk and Opportunities
1. Base Case Risk
   Project timeline not meeting the funding deadline resulting in exposure of Council to the part/full
   project cost and needing to fund this from Council reserves or future budgets.
    a.   Triggers:
          i.      Delay in commencement of construction works.
          ii.     Inability to deliver the approved scope due to delays during construction.
    b.    Drivers:
           i.    Additional community engagement absorbing programme float and budget
                 contingency.
          ii.     Deferment of endorsement at Council meetings.
          iii.    Construction period being pushed into wet season.
          iv.     Fuel cost increases.
    c.    Mitigations:
           i.    Seek time extension: SEQ Liveability Fund (Mitigation implemented and approval
                 received).
           ii. Seek time extension: Active Transport Funding (ATF) (Mitigation implemented and
               approval received).
           iii. Procurement: Undertake concurrently with engagement activities to ensure a quick
                release of tender package to the market.
           iv. Approval: Recommending contract award direct through CEO to avoid time delays
               with Council meetings.
           v. Rescoping: removal of works south of Lorikeet Drive cul-de-sac.



                                                                                           3|Page

Page 4

2.   Base Case Opportunities
     a.    Existing infrastructure: The project provides the opportunity to address inadequacy and
           requirement for emergent works to repair storm water assets prior to/during project
           implementation. Further project timeline delays and cost impacts.
     b.    Leverage funding structure: As the ATF grant is for construction only funding, matching
           the SEQ Liveability contribution. The potential exists to expand the scope of works using
           council reserves, matched by the ATF grant, to address emergent and repair works.
3.   Scenario Analysis

The following table further details alternative scenarios and the differentiated risks anticipated.
Scenario                    Description                      Likely Outcome
Base case - construction    Current Scope, Programme,      Re-instates programme float as stormwater
commencement mid-           Budget/funding - no mitigation renewal opportunities have been factored into
October (working                                           new programme but not recommended to
assumption: approvals of                                   proceed, project budget contingency mostly
EOT from both funding                                      consumed.
bodies)
                                                             Reputational damage associated with project
                                                             continuation in spite of immediate resident
                                                             resistance, particularly without implementing
                                                             recommended design changes influenced by
                                                             community engagement activities.
Adjust as per               Implement mitigations, actively Re-instates project float, enable more time to
recommendations             enhance opportunities           close out community interactions, minimise
                                                            Council exposure to project costs, maintain
                                                            opportunity to leverage funding structure to
                                                            deliver more at lower cost to council, and
                                                            reduces reputation damage risk by including
                                                            community requests and/or suggestions into
                                                            the project where possible.
Further recommendations Additional Community                Project will need to be fully funded by Council.
outside of those drafted by Consultation and or significant
                                                            Alternative design treatments will likely be more
staff                       change to planning and design
                                                            expensive than the currently proposed project.
                            approach
                                                            Delays to delivery of walking and cycling
                                                            infrastructure.
Do not proceed              Stop working on design and       Council will need to fund works to date at an
                            cancel planned construction      approximate value of $210k.
                            works.
                                                             May damage relationships with funding bodies
                                                             and potentially limit further funding
                                                             opportunities.
                                                             Reputational damage for not following through
                                                             with Walking and Cycling Strategy objectives
                                                             and negative impact on future projects
                                                             proposals across the shire.
                                                             Loss of funding for "practical" components of
                                                             the projects such as construction of shared
                                                             pathway and rectification of stormwater
                                                             infrastructure.
                                                             Delays to delivery of walking and cycling
                                                             infrastructure.

Following is an update to Attachment 8 (that was provided in the original report):

                                                                                                 4|Page

Page 5

5|Page

stg OE ia A s o |nIiop J F[lMIlaA | 1 | Design & Procurement 248 days Tue 23/09/25 Thu 17/09/26 $$ } 2 | Instruct ADG to issue a 90% design (variation to scope) 25 days Tue 23/09/25 Mon 27/10/25 | 3 | Creation of Illustrative Design 15 days Tue 28/10/25 Mon 17/11/25 | 4 Councillor Briefing on 90% 1day Thu 27/11/25 Thu 27/11/25 I | 5 Makeup councillor briefing 1day Tue 9/12/25 Tue 9/12/25 1 | 6 Webpage Update & 90% Design iday Thu 18/12/25 Thu 18/12/25 | 1:1 with affected residents 28 days Mon 12/01/26 Wed 18/02/26 | zz Pop up 1 1day Wed 21/01/26 Wed 21/01/26 | | 9 | Popup2 1 day Tue 27/01/26 Tue 27/01/26 1 | 10 | Walkshop 1day Wed 18/02/26 Wed 18/02/26 I 11 | Feedback Collation 26 days Wed 21/01/26 Wed 25/02/26 a | 12 | Council S&O Reporting 1 day Tue 10/03/26 Tue 10/03/26 | | 13 | Council General Committee Meeting 1 day Mon 16/03/26 Mon 16/03/26 I | 14 | Council Ordinary Meeting 1day Thu 19/03/26 Thu 19/03/26 I | 15 | ADG Commence Design Review Changes 80 days Mon 15/12/25 Thu 16/04/26 — | 16 | IFC 1 day Fri 17/04/26 Fri 17/04/26 ] Council General Meeting 1day Mon 15/06/26 Mon 15/06/26 | 18 | Execute any changes requested by Councillors 20 days Tue 16/06/26 Mon 13/07/26 | 19 Prepare for Tender 25 days Tue 16/06/26 Mon 20/07/26 | 20 | Release to VendorPanel 20 days Tue 21/07/26 | Mon 17/08/26 | 21 | Evaluation 15 days Tue 18/08/26 | Mon7/09/26 | 22 | Report to Council for General Meeting 5 days Tue 8/09/26 Mon 14/09/26 CO Task D__inactive Summary I 1 External Tasks Split veveeeeeeeeeeeeees Manual Task [Ss External Milestone ° ali Pine Milestone ° Duration-only | ES“; Deadiline + Date: Thu 21/05/26 Summary eT Manual Summary ROllUP cums == Progress LS Project Summary err 1 Manual Summary eis Manual Progress es Inactive Task Start-only Cc Inactive Milestone Finish-only 1 5|Page

Page 6

6|Page

Pee tt PE A s o|n|o J F|mMIaA | 23 | Award Tender 3 days Tue 15/09/26 Thu 17/09/26 | 24 Delivery 286 days Fri 18/09/26 Tue 2/11/27 | 25 | Documentation 10 days Fri 18/09/26 Thu 1/10/26 | 26 | Pre-Start Meeting 1day Fri 2/10/26 Fri 2/10/26 Site Mobilisation 12 days Fri 2/10/26 Tue 20/10/26 | 28 | Milestone 2 - Construction Commencement 0 days Tue 20/10/26 Tue 20/10/26 | 29 | Construction 264 days Wed 21/10/26 Tue 2/11/27 | 30 | Education Campaign 40 days Tue 7/09/27. Tue 2/11/27 | 31 Handover 39 days Wed 3/11/27. Fri 31/12/27 | 32 | PC Walkthrough 3 days Wed 3/11/27. Fri 5/11/27 | 33 | Ommisions & Defect Rectifications 20 days Mon 8/11/27 Fri 3/12/27 | 34 PC 1 day Mon 6/12/27. Mon 6/12/27 | 35 | Documentation Handover 15 days Tue 7/12/27 Fri 31/12/27 | 36 | Project Completion SEQ Liveability 0 days Fri 31/12/27 Fri 31/12/27 Grant Funding Completion 131 days Fri 31/12/27 Fri 30/06/28 | 38 | Finalise Payments and Completion Documentation 66 days Fri 31/12/27 Fri 31/03/28 | 39. | Milestone 3 - Completion O days Fri 31/03/28 Fri 31/03/28 | 40 Proposed End Date - SEQ Liveability Final Acquittal 66 days Fri 31/03/28 Fri 30/06/28 Task | inactive Summary I 1 External Tasks Split teseeeeeeeeseeeees Manual Task [External Milestone ° | Milestone Oo Duration-only | «éeadiine + Project: Program v3 Date: Thu 21/05/26 Summary eT = (Manual Summary RollUP ces = Progress —__———— Project Summary errr 1 Manual Summary ent Manual Progress aa Inactive Task Start-only C Inactive Milestone Finish-only a 6|Page

Page 7

7|Page

M J J A s Oo N Oo J F M A M J J A s ° N o J F M A M J J | | Task _—sinactive Summary I 1 External Tasks Split tesseeeeeeeeseeees Manual Task [Ss Extemal Milestone ° . Milestone ° Duration-only | S«éCeeaddline + Project: Program v3 | rr | —_K——_—— EEE Le Date: Thu 21/05/26 Summary Manual Summary Rollup Progress Project Summary errr Manual Summary rents Manual Progress — Inactive Task Start-only c Inactive Milestone Finish-only J 7|Page

Page 8

8|Page

M J J A Ss ° N Do J EF M A M J J A s O° N D J E M A M J J I 20/10 31/12 a 31/03 Task [__inactive Summary I 1 External Tasks Lo Split Pee eee renee eee Manual Task fo Extermal Milestone > . Milestone Oo Duration-only | s«éeeaddline + Project: Program v3 I
5	1	1	1	11	2	2001	1852	21	26	47	ll
4	1	1	1	12	0	315	1844	1860	50	-1	
5	1	1	1	12	1	315	1864	77	25	95	Date:
5	1	1	1	12	2	402	1862	57	27	96	Thu
5	1	1	1	12	3	471	1864	139	30	96	21/05/26
5	1	1	1	12	4	834	1844	128	35	95	Summary
5	1	1	1	12	5	1456	1848	91	22	96	Manual
5	1	1	1	12	6	1555	1848	120	27	96	Summary
5	1	1	1	12	7	1681	1848	79	27	96	Rollup
5	1	1	1	12	8	2058	1844	117	35	96	Progress
4	1	1	1	13	0	845	1900	1798	34	-1	
5	1	1	1	13	1	845	1905	86	29	96	Project
5	1	1	1	13	2	937	1905	119	29	96	Summary
5	1	1	1	13	3	1171	1900	238	28	49	ern
5	1	1	1	13	4	1456	1906	91	22	49	Manual
5	1	1	1	13	5	1555	1905	120	29	95	Summary
5	1	1	1	13	6	1784	1900	238	28	43	ent
5	1	1	1	13	7	2068	1906	91	22	58	Manual
5	1	1	1	13	8	2168	1905	107	29	96	Progress
5	1	1	1	13	9	2386	1911	257	9	24	ee
4	1	1	1	14	0	845	1954	948	42	-1	
5	1	1	1	14	1	845	1964	95	22	96	Inactive
5	1	1	1	14	2	946	1963	56	23	96	Task
5	1	1	1	14	3	1455	1954	124	42	92	Start-only
5	1	1	1	14	4	1774	1958	19	28	22	Cc
4	1	1	1	15	0	845	2012	956	39	-1	
5	1	1	1	15	1	845	2019	94	23	96	Inactive
5	1	1	1	15	2	948	2019	121	23	96	Milestone
5	1	1	1	15	3	1442	2012	149	39	92	Finish-only
5	1	1	1	15	4	1782	2016	19	26	65	J
4	1	1	1	16	0	2993	2234	205	44	-1	
5	1	1	1	16	1	2993	2234	205	44	87	8|Page

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.