PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the Ordinary Meeting dated 19 March 2026 - Item 12.2) · 2026-06-09 ATTACHMENT 1 to Minutes of General Committee 9.06.2026 - Peregian Beach Active Street - Further Information

of 8

Page text shows just the words. Original shows the document exactly as it was published.

SEQ Liveability
The last possible dates for milestones as listed in the executed SEQ Liveability funding agreement,
are:
Milestone                 Last Possible Date (as                               Status
                                                 Current Approved
                          per Program
                                                 Variation Date
                          Guidelines)
Completion of             30 Jun 2027                                          Achievable
                                                     31 Dec 2027
Construction
Final Reporting           31 Dec 2027                30 June 2028              Achievable


Active Transport Fund
The last possible dates for milestones as listed in the executed ATF funding agreement, is:
Milestone                 Last Possible Date (as                               Status
                                                 Current Approved
                          per Program
                                                 Variation Date
                          Guidelines)
Commencement of           25 Mar 2026                                          Achievable
                                                    20 Oct 2026
Construction
Completion of             25 Mar 2028                                          Achievable
                                                    NIL
Construction
Acceptance of          25 Jun 2028                                             Achievable
                                                    NIL
Post-Completion Report


Current Project Program
The current program is based on receiving Council support by no later than the June Ordinary
Meeting. Construction is anticipated to begin in October 2026 with practical completion being
achieved in December 2027. The full program, including additional project consultation activities
contributing to the extension of time required is provided at attachment 8. Further delays would put
the project at significant risk, as the maximum allowable extension of time request from SEQ
Liveability has already been sought, and the chance of receiving a second extension of time past
this deadline is highly unlikely. It would also put Councils reputation with grant funding bodies at risk,
compromising future grant opportunities.
Table 1 below indicates current forecast milestone dates as per the project program.
Milestones                                   Deadline
Council Decision - General Committee         9 June 2026
IFC Design                                   13 July 2026
Award Tender                                 17 Sep 2026
Practical Completion                         6 Dec 2027
Handover – final report & funding acquittal30 June 2028
Table 1: Program Milestones




                                                                                              2|Page
Log in to download the original file

2026-06-09 ATTACHMENT 1 to Minutes of General Committee 9.06.2026 - Peregian Beach Active Street - Further Information.pdf · 659 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.