GENERAL COMMITTEE MEETING 14 AUGUST 2023
6.1 CONTRACT NO. CN00315 - FLOOD RECONSTRUCTION - PACKAGE 10 -
STORMWATER INFRASTRUCTURE REPLACEMENTS
Author Disaster Reconstruction Coordinator, Julie Calvert
Infrastructure Services Department
Index ECM / Subject / Contracting / Road Construction
ECM / Projects (T1) / CN00315 Flood Reconstruction - Package 10 -
Stormwater Infrastructure Placements
Attachments None
EXECUTIVE SUMMARY
• This report provides a tender evaluation summary and recommendation for the tender award
for the reconstruction of various stormwater Infrastructure sites which were impacted by the
February/March 2022 Flood.
• In accordance with Council procurement policy and procedure, an Invitation to Tender (ITT)
was initiated. The ITT identified that an industry briefing was required. This was considered
a mandatory requirement to properly understand the project and to validate tender
responses. The industry briefing attracted eight (8) attendees. At the response closing time
on 29 June 2023, six (6) tender submissions were received, two (2) of which were assessed
as non-conforming.
• The tender evaluation panel completed the evaluation process and considered the tender
from SGQ Pty Ltd to be the most advantageous to Council, presenting the best value for
money.
• The reconstruction is funded by Queensland Reconstruction Authority (QRA) using funds
from both state and federal government. The site is an eligible structure under the
Reconstruction of Essential Public Assets (REPA) and funded under the Disaster
Reconstruction Funding Arrangements (DRFA) grant.
RECOMMENDATION
That Council note the report by the Disaster Reconstruction Coordinator to the General Committee
Meeting dated 14 August 2023 and:
A. Award Contract No. CN00315 for Flood Reconstruction - Package 10 - Stormwater Infrastructure
Replacements to SGQ Pty Ltd; and
B. Authorise the CEO to negotiate the final Contract with SGQ Pty Ltd; and
C. Authorise the CEO to amend the contract up to 11.5% of the total contract value.
Page 334 of 476
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (b1337d84ed.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.