GENERAL COMMITTEE MEETING 14 AUGUST 2023
The total proposed capital works adjustment is $11.9 million, as outlined in the table below.
Item Amount
($’000)
Original Budget $39,418
Carryovers $9,874
Emergent Works and Variations $2,041
Proposed Revised Capital Expenditure Budget $51,333
The following table summarises the proposed revised 2023/24 capital budget by program, with the
full list contained in Attachment 2.
Proposed BR
Original
Program Carryover Emergent 1 Total
Budget
Budget
Capital Works
Bridges 5,885 435 6,320
Cemeteries 40 192 232
Coastal Canals and Waterways 3,310 765 847 4,923
Commercial Land & Properties 255 255
Community Facilities 1,414 914 177 2,506
Corporate Buildings 661 375 1,036
Environmental Assets, Bushland,
252 255 1,017 1,524
Tracks and Trails
Gravel Road Network 475 150 625
Holiday Parks 120 93 213
Libraries and Galleries 260 212 472
Parks & Playgrounds 1,310 839 2,149
Pathways & Boardwalks 1,579 914 2,493
Public Amenities 1,491 1,491
Public Transport Infrastructure 481 50 532
Sealed Roads Network 6,718 1,018 7,736
Sports Ground and Facilities 170 476 646
Stormwater Drainage 3,860 624 4,485
Streetscapes and Road
200 116 316
Corridors
Transport and Infrastructure
977 151 1,128
Management
Waste Management 3,019 366 3,385
Other Works
Asset Management 2,380 182 2,562
Fleet - Plant Replacement 1,393 1,034 2,427
Strategic Planning 1,823 320 2,143
ZEN Program 400 137 537
Loan Redemption 1,200 1,200
Grand Total 39,418 9,874 2,041 51,333
Page 405 of 476
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (b1337d84ed.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.