GENERAL COMMITTEE MEETING 14 AUGUST 2023
Status Quarter 1 Quarter 2 Quarter 3 Quarter 4
(July – Sept (Oct – Dec 2022) (Jan – Mar 2023) (Mar – June 2023)
2022)
Not started 7 1 3 1
Behind Schedule 15 15 8 16
On Track 72 73 72 30
Completed 2 7 13 49
In addition to the Council Officer comments at Attachment 1, additional commentary is provided in
relation to initiatives marked as "on track" which which may be on-going and relisted as initiatives in
the new 2023-24 Operational Plan. The following analysis can be provided for behind schedule, not
started or projects requiring further commentary:
1.4 – Implementation of the Waste Strategy is behind schedule however Councillor workshops and
public consultation has occurred. The Waste Strategy is expected to be adopted in September 2023.
1.5 – Review of the Noosa Design Principles is progressing and targeted consultation has occurred.
The initiative has been incorporated in the new 2023-24 Operational Plan.
1.7 – SEMP is is on track with an operational environmental permit approved and contract awarded.
This initiative has been incorporated in the new 2023-24 Operational Plan and will continue to be
monitored for delivery in 2023.
1.7 – Household Recycling Decontamination initiative has not commenced due to resourcing and
will be implemented as an action from the Waste Strategy. This initiative has been incorporated in
the new 2023-24 Operational Plan.
3.2 – DMP project is behind schedule however the LDMP was adopted by the LDMG in February
and is expected to presented to Council in Q1/Q2. This initiative has been incorporated in the new
2023-24 Operational Plan.
4.1 – Amendments to the Planning Scheme and progress of the Place Making projects were
previously behind schedule however both items are now progressing and have been incorporated in
the new 2023-24 Operational Plan.
4.2 – Noosa Woods Jetty project behind schedule, draft consultancy report prepared, consultation
process to commence in 2023-24 subject to resourcing. This initiative has been incorporated in the
new 2023-24 Operational Plan.
4.5 – Community Indicators/performance measures, performance measures have been included in
the development of the new Noosa Council Corporate Plan 2023-28 and will be further reviewed.
Initiatives to develop a performance measurement framework and implement a new corporate
reporting system have been incorporated in the new 2023-24 Operational Plan.
4.7 - Cemeteries Management Plan not commenced however the requirement for a full cemeteries
management plan has been incorporated in the new 2023-24 Operational Plan.
5.1 – Customer Service Charter review behind schedule as result of the reallocation of the project
following the organisational realignment. This initiative has been incorporated in the initiative to
develop a customer experience program which has been incorporated in the new 2023-24
Operational Plan.
Page 434 of 476
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (b1337d84ed.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.