Corporate Plan Theme - Long Term Planning for Noosa Shire Operational Plan 22/23
Corporate Plan Key Operational Initiatives Outcomes Responsible Update Q4 Status
Focus Areas Areas
Landfill Treatment Options Optimisation of site Waste Invitation to Quote released for various options and On track
Plan operations and Services pre-feasibility analysis. Waste Team to progress The investigation of
incorporation of various options over the coming quarter. further options to
treatment options to increase waste
maximise life of landfill site diversion from landfill
is incorporated in
23/24 Oper. Plan
4.5 Develop and Note: To be considered in To measure the CEO KPI’s developed and included in the new Corporate Completed
report on community the development of the new environmental, social, and Plan.
sustainability Corporate Plan economic health across
indicators communities
4.6 Meet the principles Ongoing Support of the A community led framework Environmental Ongoing partnership and collaboration with NBRF, On Track
of the UNESCO Man Noosa Biosphere Reserve that meets the balance Services including Koalas on the Move campaign and On-going. Providing
in the Biosphere Foundation between environment and providing input into PHD research projects currently ongoing support to the
Program sustainable human underway by University of the Sunshine Coast. Noosa Biosphere
development Second Sustainability Forum held in May with Council Reserve Foundation is
staff representatives and Councillors in attendance to incorporated in the
assist in the development of the NBRF operational 23/24 Oper. Plan
plan.
4.7 Establish Finalise development of Asset management Asset Parks and Playground AMP was adopted at the April Completed
functional Asset asset management plans objectives are met, and full Planning round of meetings by Council.
Management Plans for major asset classes by suite of Asset Management
for all Council asset completing the Parks and Plans completed
classes Playgrounds AMP
Complete a Cemetery Maximise use of existing Community Initial research has identified need for full Cemeteries Not started
Management Plan cemetery sites and plan for Connection Plan and the requirement for an expert consultant. The completion of the
future cemetery needs Cemeteries Plan to commence in 23/24 budget. No Noosa Cemeteries
further work will be undertaken in 22/23. Plan is incorporated in
the 23/24 Oper. Plan
Page 462 of 476
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (b1337d84ed.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.