ORDINARY MEETING MINUTES 18 MAY 2017
8. There must be no electrical reticulation system carrying electricity in excess of 24 volts
beyond the revetment wall unless all switches and power outlets are positioned above
the 1%AEP flood level.
9. Lighting associated with the use must be designed, installed, operated, and maintained
in accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor
Lighting.
10. Wastewater and sullage must only be disposed of at approved pumpout facilities.
11. The mooring facility must not be utilised for live-aboard purposes.
12. Any construction and post construction activity is not to impact on the condition of the
waterway, and is to be conducted so as not to breach the Environmental Protection Act
EPA (1994) and the Environmental Protection (Water) Policy 2009.
13. Certification by a Registered Professional Engineer of Queensland that states that the
works have been constructed in accordance with best practice methods and are
structurally sound must be submitted to Council. This certification must be submitted
to Council within three (3) months of the date of this approval. A final inspection and
approval of the structure by Council’s Inspector is also required. Please contact
Council’s Planning Assessment Section (Development Audit & Response Officer
0428738563) to arrange the inspection.
14. After completion, the proposed works must be maintained in a sound state of repair in
accordance with the approved plans.
15. All necessary State government approvals relating to this development must be
obtained.
Page 7 of 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.