Development Application Part 3 - Construction Management Plan, Floor Plans · OPW11/0335

Plans and drawings: the text below has words only, no drawings.

Very large file (10.1 MB): may take a few minutes to open.

Log in to see the plans as drawn
                                                                        contrast constructions pty ltd licence: 1012338




^ con'rast
                                                                                abn: 20 100 835 934 acn: 100 835 934
                                                                                      p 07 3862 2366 f 07 3862 2944
                                                                           unit 4/ 10 hudson road  albion  Q 4010
                                                                                   po box 21 15   windsor  Q 4030
                                                                          mai0contrastcom.au      www.contrast.com.au




  Business Name                                  Contrast Constructions Pty Ltd

  Client                                         Scanlon Property Group Pty Ltd

                                                 Essence on Peregian 215 - 219 David Low Way Peregian
  Project Title
                                                 Beach

  Document title                                 Construction Management Plan (CMP)

  Date                                                 30/09/2011               Issue                    A




 Introduction

      This Construction Management Plan (CMP) is to satisfy general condition clause 93 of the planning and
     environment court judgement (No 2587 of 2008)



     This Construction Management Plan (CMP) is the prime document for the management of works
     undertaken at Essence of Peregian 215 - 219 David Low Way Peregian Beach

      The aim of the plan is to ensure that appropriate measures have been considered for site access,
     egress, storage and the operation of the site during all phases of the construction process in a manner
     that respects adjoining owner's property rights, maintains public safety, minimises disruption to pedestrians
     and vehicular traffic within this locality and protects services.


 Scope of works
         The Project is located at 215 - 219 David Low Way Peregian Beach

         The works includes the demolition of existing structures, remove trees and construct a two storey with
         underground parking mixed commercial and residential property.


 Works Program
         The works program for the project is detailed in Attachment A. The works program will be updated
         progressively and records kept in project files.


 Working hours
         Approved working hours are lam to 6.30pm Monday to Saturdays (excluding public holidays)

         Works outside these hours will require written approval from the Council and nearby residents and
         businesses will be advised of changed hours.

Used in these records

About this file

File size
10.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application Part 3 - Construction Management Plan, Floor Plans.pdf · 10.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.