Q4 · 1 April to 30 June 2026 · plan 2025-26
On Track 81-90%
The fuel reduction and planned burns program has progressed well this year with over half of the activities conducted for the calendar. Training and accreditation have occurred for Council staff and Kabi Kabi Land & Sea Rangers through a joint training program.
- Lead service, as extracted
- Strategy & Environment
- Reported start / end
- 07-25 / 12-26 (source month-year wording)
Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.
98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.