2.5.2 · Continue to undertake the staged implementation of master plans for the Cooroy and Noosa District Sports Complexes to improve sport and recreation facilities and increase participation in sports.

About the archive ↗

Plan 2025-26 · each observation is Council’s published description. Progress ranges remain ranges; “Completed” is an as-reported status, not an independent audit.

All published progress ↗Explicit report-back requests ↗

Q4 · 1 April to 30 June 2026 · plan 2025-26

On Track Ongoing Initiative

The Cooroy Oval lighting project is complete. The Cooroy Gymnastics extension project continues to progress, as does the completion of the Noosa Netball Clubhouse at NDSC, both being delivered as projects arising from the precinct master planning process.

Lead service, as extracted
Community Services
Reported start / end
07-25 / 06-28 (source month-year wording)

Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.

98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.