3.1.1 · Advance the Sustainable Procurement Policy through the ongoing implementation of policy, procedure and education, and develop a reporting framework for monitoring and measurement.

About the archive ↗

Plan 2025-26 · each observation is Council’s published description. Progress ranges remain ranges; “Completed” is an as-reported status, not an independent audit.

All published progress ↗Explicit report-back requests ↗

Q4 · 1 April to 30 June 2026 · plan 2025-26

Minor Disruption Ongoing Initiative

Procurement branch resourcing impact has meant that working group has been placed on hold. PPA procurement opportunity will continue to be progressed.

Lead service, as extracted
Corporate Services
Reported start / end
07-25 / 06-26 (source month-year wording)

Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.

98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.