4.2.3 · Review and manage the Tourism Noosa Partnership E Agreement to align with Destination Management Plan outcomes and develop a clear transition roadmap to support implementation.

About the archive ↗

Plan 2025-26 · each observation is Council’s published description. Progress ranges remain ranges; “Completed” is an as-reported status, not an independent audit.

All published progress ↗Explicit report-back requests ↗

Q4 · 1 April to 30 June 2026 · plan 2025-26

Completed 100%

Tourism Noosa Roadmap: Completed and endorsed by Council at its Ordinary Meeting on 19 December 2025. Partnership Agreement and Funding Deed: Adopted by Council at its Ordinary Meeting on 18 June 2025. Project Group to meet with operational staff to go through both documents in detail.

Lead service, as extracted
Strategy & nvironment
Reported start / end
09-25 / 12-25 (source month-year wording)

Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.

98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.