Q4 · 1 April to 30 June 2026 · plan 2025-26
On Track 31-40%
Tenders have been issued for two work packages including Black Mountain Road and Nandroya Road. Remaining packages will be two for drainage structures, one for roads and one for Black Pinch Rd. These will be issued for tender within the next eight weeks, with contracts anticipated to be in place before the end of calendar year. All works are programmed for completion by June 30, 2027.
- Lead service, as extracted
- Infrastructure Services
- Reported start / end
- 07-25 / 06-27 (source month-year wording)
Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.
98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.