Q4 · 1 April to 30 June 2026 · plan 2025-26
On Track 61-70%
Implementation of identified actions of the Regional Cascading Risks and Critical Infrastructure Failure Project (CIF) underway for Council key assets and services. Adaptation Game launched with regional partnership. Knowledge sharing of CIF findings across government agencies continues.
- Lead service, as extracted
- Strategy & Environment
- Reported start / end
- 07-25 / 12-26 (source month-year wording)
Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.
98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.