Q4 · 1 April to 30 June 2026 · plan 2025-26
On Track 51-60%
Redesign for Sunshine Creek embankment stabilisation has been completed with a focus on slope stability and only necessary creek erosion protection. Contract progressing well. Ground conditions and wet weather is necessitating some minor design variations, contractor methodology changes and extensions of time. SARA approvals completed with slope stability and minimal creek bed action. Targeting early acquittal for grant funding with plan to complete works in October 2026.
- Lead service, as extracted
- Infrastructure Services
- Reported start / end
- 07-25 / 10-26 (source month-year wording)
Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.
98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.