4.8.6 · Progress the design for the replacement of the Main Beach Sea Wall to be more resilient to future climate events.

About the archive ↗

Plan 2025-26 · each observation is Council’s published description. Progress ranges remain ranges; “Completed” is an as-reported status, not an independent audit.

All published progress ↗Explicit report-back requests ↗

Q4 · 1 April to 30 June 2026 · plan 2025-26

On Track 61-70%

Revised design Includes adaptable construction and incorporating improved aesthetics and amenity to better align with stakeholder expectations. Revision to timing and cost under negotiation with Qld Reconstruction Authority (QRA) and National Emergency Management Agency (NEMA). Design revision to consider raise and increase reach of seawall and augment Sand Recycling System continue. More formal engagement with internal and external stakeholders is planned to inform functional and aesthetic design outcomes.

Lead service, as extracted
Infrastructure Services
Reported start / end
07-25 / 06-28 (source month-year wording)

Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.

98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.