Q4 · 1 April to 30 June 2026 · plan 2025-26
On Track 81-90%
Rectification works are ongoing at Noosa Leisure Centre and Cooroy Library, while works at The J are completed. Noosaville Library roof replacement and solar procurement have been completed. Historical water usage data currently being collated, and collaboration with Unitywater continues to improve water billing transparency and efficiency opportunities around smart metering.
- Lead service, as extracted
- Strategy & Environment
- Reported start / end
- 07-25 / 06-26 (source month-year wording)
Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.
98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.