Q4 · 1 April to 30 June 2026 · plan 2025-26
On Track 51-60%
Asset Management Framework implementation on track within available resources and continuing. Progress is tracked through the Asset Steering Committee. Tasks will extend beyond the current financial year as per the Strategic Asset Management Plan. Workshops are scheduled with Council to review the State of the Assets and further consider the asset management framework moving forward.
- Lead service, as extracted
- Infrastructure Services
- Reported start / end
- 12-24 / 12-27 (source month-year wording)
Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.
98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.