5.9.1 · Deliver the budgeted Capital Works program across Shire to budget, time, and quality expectations.

About the archive ↗

Plan 2025-26 · each observation is Council’s published description. Progress ranges remain ranges; “Completed” is an as-reported status, not an independent audit.

All published progress ↗Explicit report-back requests ↗

Q4 · 1 April to 30 June 2026 · plan 2025-26

Minor Disruption 51-60%

Progress on the capital works program is reported to the monthly Capital Works Executive, and a quarterly report distributed to the full Council indicating progress year to date. The June report is indicating a total spend of $34.0m (68% of BR2 Approved Budget) with a further $27.7m in commitments. Average project progress is at 82% across the 122 projects within the CWP, with 63% of projects over 90% complete.

Lead service, as extracted
Infrastructure Services
Reported start / end
07-25 / 06-26 (source month-year wording)

Source discrepancy: detailed rows and introductory summary differ. On Track: 52 detailed rows versus 53 in the summary. Minor Disruption: 17 detailed rows versus 16 in the summary. The progress chart counts detailed rows; inspect page 2 of the original summary before drawing conclusions.

98 unique initiative rows reconcile to the report’s declared 98 initiatives. Column text is extracted from the printed layout; consult the original page for wrapped wording. This does not establish a deadline breach or the cause of reported disruption.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.