Public Question Time Applicant: Pat Spicer

← Meeting agenda & transcript

See the votes on this matter →

What was decided?

The minuted decision sequence

No separately labelled carried Council Resolution has been identified here. Read each formal event and the complete item minutes; a lost motion is not necessarily the final outcome.

Read complete item-specific minutes
QUESTION 1
What was the total cost for site investigations for 62 Lake Macdonald Drive, Cooroy and the ongoing consultations, plans and reports from companies including Murray and Associates, Covey and Associates, Environmental Advisors (contamination), North Coast Environmental Services,  Holland Traffic Engineering, Austrac Traffic Count, Hydra Logic, Auspower that formed the Civil Works Package and Remediation Works Package up to work commencing on site on 4 September, 2025?  (Please do not include any grants in this total figure).

RESPONSE BY KIM RAWLINGS, DIRECTOR STRATEGY & ENVIRONMENT

To date approximately $375,000 has been spent on plans, reports, investigations noting the project is still live and yet to be completed.  

QUESTION 2 
What was the total amount of grant funding received to offset the costs?

RESPONSE PROVIDED BY KIM RAWLINGS, DIRECTOR STRATEGY & PLANNING

$178,000 of that grant funded to offset these costs from the Federal Housing Support Program.

The meeting adjourned at 10.22am.
The meeting resumed at 10.33am.


This summary follows this item’s minutes. The established voting totals use their existing method while differences are checked against the full records.

What was said?

Named discussion on NoosaWatch TV

These actual transcript passages match the item’s wording. The start and end of the item’s discussion are not yet confirmed; these excerpts are not measured item airtime or exact decision moments.

Pat Spicer19:36
Thank you. Through the Chair. My name Pat Spicer. Is the background information. Site investigations started as early as 2019 on 62 Lake Macdonald Drive, Cooroy. The budget allocation for site investigations was $500,000 in the 2023-24 budget. The allocations for delivery costs, remediation and civil works was $3.3 million in the 2024-25 budget. My question. What's total the cost for site investigations for 62 Lake Macdonald Drive, Cooroy, and the ongoing consultations, plans and reports from companies including Murray and associates, covey and associates, environmental advisors for the contamination, north Coast environmental services, Holland traffic engineering, Austrac Traffic Count, Hydra Logic, Auspower, that Council form the civil works package and remediation works up package to the work commencing on site on the 4th of September 2025. Thank you, very good.
Pat Spicer21:16
Background information. Council was successful in,000 Federal grant towards these costs from the Federal housing support program which was detailed in the March Housing Strategy updates. What was the of grant funding received to offset the costs?
1 suggested discussion start time
  • 1172.0 seconds on the council source timeline · Recording time not yet verified. The end of the discussion is not yet confirmed.

The supporting record

Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.