Skip to the record
For the highest quality transcripts.
Item 13.2.2026-11-19 · OrdinaryOfficial item record

Further Report - Peregian Active Street Update

Final resolution: Carried

That Council A. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian B… Full wording ↓

For 5: Jessica Phillips, Amelia Lorentson, Tom Wegener, Nicola Wilson, Karen Finzel. Against 1: Brian Stockwell.

Watch Amelia Lorentson discuss the topic ↗
← Meeting agenda & transcript

See the votes on this matter →

What was decided?

Final supported resolution

That Council

A. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project; and

B. Not proceed with Coastal Pathway Stage 1 Peregian Beach South and seek that the South East Queensland Liveability funding be reallocated to an existing priority project/s eligible within the funding criteria. 

Carried.

Official item minutes · Event 4

1MotionOutcome not confirmed

Moved: Brian Stockwell · Seconded: Karen Finzel

That Council

A. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project;

B. Support the project 'Coastal Pathway Stage 1 - Peregian Beach South' in place of the 'Peregian Beach Active Street' project;

C. Proceed with delivering the 'Coastal Pathway Stage 1 - Peregian Beach South Design', (Attachment 1) utilising the approved SEQ Liveability funds noting the risks associated with the recommended scenario; and 

D. Pending successful outcome of Active Transport Fund (ATF), proceed with further expansion of the proposed scope as indicated in the design, as provided at Attachment 1.

Official minutes · section 5

2Procedural MotionCarried

Moved: Jessica Phillips · Seconded: Tom Wegener

That the meeting be adjourned for 5 minutes. 

Carried.

Official minutes · section 13

3MotionLost

Moved: Brian Stockwell · Seconded: Karen Finzel

That Council

A. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project;

B. Support the project 'Coastal Pathway Stage 1 - Peregian Beach South' in place of the 'Peregian Beach Active Street' project;

C. Proceed with delivering the 'Coastal Pathway Stage 1 - Peregian Beach South Design', (Attachment 1) utilising the approved SEQ Liveability funds noting the risks associated with the recommended scenario; and 

D. Pending successful outcome of Active Transport Fund (ATF), proceed with further expansion of the proposed scope as indicated in the design, as provided at Attachment 1.

Lost.

Official minutes · section 22

4Council ResolutionCarried

Moved: Amelia Lorentson · Seconded: Karen Finzel

That Council

A. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project; and

B. Not proceed with Coastal Pathway Stage 1 Peregian Beach South and seek that the South East Queensland Liveability funding be reallocated to an existing priority project/s eligible within the funding criteria. 

Carried.

Official minutes · section 35

Read complete item-specific minutes
Cr Frank Wilkie
"I, Cr Frank Wilkie inform the meeting that I have a perceived conflict of interest for Item 13.2 - PEREGIAN ACTIVE STREET UPDATE on this agenda as the matter involves a proposal for a new footpath in Lorikeet Drive, Peregian and I and a close relative, my mother, live in nearby streets that connect onto Lorikeet Drive.  Although I believe I can make a decision in the public interest, to avoid perceptions of a conflict of interest, I choose to leave the meeting room while this matter is discussed and voted upon."

Cr Frank Wilkie left the meeting.
Cr Stockwell assumed the Chair. 

Motion
Moved:               Cr Brian Stockwell
Seconded:         Cr Karen Finzel         

That Council
  1. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project;
  2. Support the project 'Coastal Pathway Stage 1 - Peregian Beach South' in place of the 'Peregian Beach Active Street' project;
  3. Proceed with delivering the 'Coastal Pathway Stage 1 - Peregian Beach South Design', (Attachment 1) utilising the approved SEQ Liveability funds noting the risks associated with the recommended scenario; and 
  4. Pending successful outcome of Active Transport Fund (ATF), proceed with further expansion of the proposed scope as indicated in the design, as provided at Attachment 1.

Procedural Motion
Moved:Cr Jessica Phillips
Seconded:Cr Tom Wegener
That the meeting be adjourned for 5 minutes. 
Carried.
For:Cr Jessica Phillips, Cr Amelia Lorentson, Cr Brian Stockwell, Cr Tom Wegener
Against:Cr Karen Finzel, Cr Nicola Wilson

The meeting adjourned at 12.50pm.
The meeting resumed at 12.55pm.

Motion
Moved:Cr Brian Stockwell
Seconded:Cr Karen Finzel
That Council
  1. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project;
  2. Support the project 'Coastal Pathway Stage 1 - Peregian Beach South' in place of the 'Peregian Beach Active Street' project;
  3. Proceed with delivering the 'Coastal Pathway Stage 1 - Peregian Beach South Design', (Attachment 1) utilising the approved SEQ Liveability funds noting the risks associated with the recommended scenario; and 
  4. Pending successful outcome of Active Transport Fund (ATF), proceed with further expansion of the proposed scope as indicated in the design, as provided at Attachment 1.
Lost.
For:Cr Brian Stockwell, Cr Nicola Wilson
Against:Cr Karen Finzel, Cr Jessica Phillips, Cr Amelia Lorentson, Cr Tom Wegener

The meeting adjourned 1.06pm
The meeting resumed at 1.39pm

Council Resolution
Moved:Cr Amelia Lorentson
Seconded:Cr Karen Finzel
That Council
  1. Note the report by the Project Manager to the General Committee dated 10 November 2026 and the further report to the Ordinary Meeting dated 19 November 2026 regarding an update on the Peregian Beach Active Street Project; and
  2. Not proceed with Coastal Pathway Stage 1 Peregian Beach South and seek that the South East Queensland Liveability funding be reallocated to an existing priority project/s eligible within the funding criteria. 
Carried.
 For:Cr Karen Finzel, Cr Jessica Phillips, Cr Amelia Lorentson, Cr Tom Wegener, Cr Nicola Wilson
 Against:Cr Brian Stockwell

Cr Frank Wilkie returned to the meeting and resumed the Chair.

This summary follows this item’s minutes. The established voting totals use their existing method while differences are checked against the full records.

What was said?

Named discussion on NoosaWatch TV

These actual transcript passages match the item’s wording. The start and end of the item’s discussion are not yet confirmed; these excerpts are not measured item airtime or exact decision moments.

I note the report by the project manager to the General Committee date and attempt 10th of November 2026 and the further report to the Ordinary Meeting dated 19th of November 2026 regarding an update on the pigeon beach active street project and b not proceed with coastal pathway stage one Peregian Beach south and seek that the South East Queensland liveability funding be reallocated to an existing priority project active street or projects eligible within the funding criteria. I'll keep this really brief we've had a lot of conversations it's been a really long morning I think I just believe the decision that the motion in front of us is the right decision for Noosa and for Peregian. The motion simply keeps the funding working for so rather than risk losing it, we redirect it to another shuttle ready project, priority project within our Shire. So the money stays here in Noosa and our residents still benefit. I'm going to just jot some stats that were given to us early in this debate. 52 properties were contacted during the week, 26 were home. And the overall sort of consensus was 46% in support of the original proposal, 23% was cautious, and then there was the rest, 31% that had hesitations or didn't. I think the data alone, and also just the questions that have been raised by Councillors and by residents over the last week, to me supports the motion that we've got in front as the responsible pathway. And I want to reiterate just what was raised by Tom and Jess in terms of that we need to give Peregian essentially the time that it needs. Again I keep coming back to understand there is a transport cycle plan but the residents still are not clear in terms of how stage one connects to the village they're not sure how all this is connected. Too many questions remain unanswered so this notion gives us the opportunity to get that part right and just reflect on the process over the last six months. Just ask everyone to support this alternative motion. I think it's just the right decision for Noosa and for the Peregian residents. Anyone else like to talk to the. Motion?
Yeah, I've got a lot to say, but I know that's for the Council. Yeah, good morning, afternoon. Thank you for the opportunity to speak to this. There's a lot of learnings in this. It's been a complex, convoluted and challenging project. I acknowledge the work of all the staff and the over and above that, you know, you've all done and the team I want that to be passed on. I'd thank also the community for being involved and for making the time available to speak with staff, email each one of us and be proactively involved in what's happening in their street. I'd also like to thank my fellow Councillors for the amount of time and effort that everyone has put into this. We all know that there's going to be losses and there's going to be wins. I guess in the role of leadership it's about how do we challenge and question and eventually make decisions and ultimately where they fall. I acknowledge the strategy from the Walking and Cycling Strategy as the higher document speaking into this. There was a broad community engagement everything in that strategy supported higher level decision-making. I like the idea that through this process and the extra work from the staff that there was a compromised position reached with the extra work and the further engagement so I matter value the time spent regarding that matter and I do give that a lot of weighting however I do think I've got to as a leader in the space and make a very challenging decision rise to more those higher levels of what will speak to informing this decision as we know risk there's always wins I'm standing at an intersection today that you know in hindsight perhaps things could have been better navigated and I think as a group it's good to pause and review and I think this is a very good opportunity to look at like how we could have done this differently and inform how we move forward into the future. I understand the pedestrian pathway at the 1.5 is not probably the higher standard where we're going in that higher level because we talk across the Shire the whole of the Shire about our health and well-being access to you know connectivity um access for you know, on wheels access for mothers with prams people on bikes so I guess with all the things before us today I think we can do better in terms of delivering what will become an asset of Noosa Shire Council now and into the future we all know those assets like project about a 25 year forward I certainly do not want to support um an asset that may not serve us effectively for the next 25 years forward so based on the decision here before us today I will not be supporting um this um Peregian active street update with the hope that we can diversify the funding to other projects within the Shire understanding also there is a cost back to Council with regards to monies that have to be re-delegated understanding also that there will be returning funds and this is where the challenge lies from an economic perspective but in the terms of the role of the leader these are the challenging decisions we have to make so um following also strategic directions that have been ratified by Council that have included vast community engagement in the broader sense but also acknowledging those technical expertise of our staff you know I am not an infrastructure builder I do not know those technical details and I rely on our well-qualified staff to provide that information so there's a lot of challenges again about prioritisation of projects I have repeatedly brought this up in my two terms that I've spent from day one I've asked repeatedly that we look at how we do this better with priority prioritisation of projects I will continue to raise that matter because I think somewhere in all of this that has somehow also played into that um. And yeah I guess that's all I have to say right now and I guess thank you to everybody listening for listen.
We're about to connect back on. Not really. Okay, so welcome back. We are debating the motion in front of us in regard to the Peregian active street update report, and my understanding has is everyone has talked to the motion other than Councillor Finzel. I think you have only asked questions. Would you like to talk to the motion?
Mr close? No. Okay. Motion those in favour? That's unanimous. Thank you. Let's bring this to item 13.2, which is further report on the Brooklyn active street update. So I do have the same topic of interest. No need to read it out. I don't need to read it out. Thank you. I'll leave the meeting room.
Those in favour? Councillor Lorentson, Phillips, Finzel. Those against? Councillor Wilson, Stockwell, Wegener and Wilkie. Is lost. It now brings us to consideration of committee recommendations. 11.1.1 Audit and Risk Committee recommendations dated 23rd of October 2026.11.1.1 Queensland Audit Office QAO closing report. 11.1.2 2025-26 annual financial statements. 11.1.3 Noosa Shire Council 2025-26 annual report. 11.1.4 financial management assurance program year one work plan. 11.1.5 governance and policy update. 11.1.6 corporate culture update 2526.11.1.7 workplace health and safety report 2526.11.1.8 Queensland Audit Office managing cyber security. Risk self-assessment. 11.1.9 ICT Cyber Risk Report. 11.1.10 rates and charges debt management and recovery. 11.1.11 fringe benefits tax project update. 11.1.12 Super on Contractors project update. 11.1.13 is all these audit committee recommendations en bloc. May I have a mover? Seconder? Moved. Councillor Wilson. Seconder? Councillor Phillips. All in favour? That's carried unanimously. Moved. We now come to the General Committee recommendations dated 6th of October 2026. Capital program 2627 delivery status report 11.2.2. Planning applications decided by delegated authority September 2026.11.2.3. Noosaville community battery project report. 11.2.4. Operational plan 2026-27. Quarter one, quarterly reporting. 11.2.5. Bridgerton active street. I'd like to declare a conflict of interest. So, my Councillor Frank Wilkie informed the meeting I have received conflict of interest for item 11.2.5, bridgerton active street update. On this agenda, as the matter involves a proposal for a new footpath in Lorikeet Drive, Peregian. And I and a close relative, my mother, live in nearby streets that connect onto Lorikeet Drive, although I believe I can make a decision in the public interest to avoid perceptions of a conflict of interest, I choose to leave the meeting room while this matter is discussed and voted upon.
1 suggested discussion start time
  • 7367.0 seconds on the council source timeline · Recording time not yet verified. The end of the discussion is not yet confirmed.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.