10.
41,
12.
13.
9.4, Low impact construction techniques are used around vegetation to minimise
interference with the vegetation.
Cleared vegetation is to be suitably pracessed by one of the following methods and removed
from the site:
10.1. Processing through a woodchipper or shredder. The resulting mulch is to be,
stockpiled loose in heaps of less than 1000 cubic metres, less than 2.5 metres high
with a minimum of 10 metres between edges of heaps.
10.2. Disposal for firewood.
10.3. Disposal for landscaping purposes.
10.4. Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
10.5. The applicant is advised that burning off is an unacceptable meéthod of disposal.
Dense screening vegetation shall be planted to the raised front setback area to the south
side of the driveway and planted in accordance with Council’s Planning Scheme Policy
PSP3 Landscaping Plants and Guidelines.
A mix of native landscaping such as ground covers, shrubs and trees shall be provided for a
width of 3m from the seaward boundary and planted in accordance with Council's Planning
Scheme Policy PSP3 Landscaping Plants and Guidelines
Landscape structures including retaining walls shall be setback a minimum of 6m from the
seaward boundary, except for the swimming pool, which shall be setback a minimum of 3
metres,
General
14.
15,
16.
17.
18.
19.
Buildings and structures {including swimming pools, sheds, tennis courts or outbuildings)
shall not be constructed under overhead electricity transmission lines, or within any
easements,
The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
The proposed development shall have all kitchen, laundry and bathroom fittings that comply
with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation
Rating System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres
per min. Dishwashers and washing machines are excluded from this requirement.
All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
External colours and finishes of the building shall comprise of muted/environmental tones
that blend with the natural environment.
Gates must not be installed along the rear property boundary.
Demolition or Relocation of Existing Dwelling
20.
21.
Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be
protected from damage and made safe to the standard required by the regulatory authority.
All infrastructure must be disconnected, capped or sealed including:
21.1. electricity meters removed and electrical wires disconnected; and
21,2, telephone lines are disconnected; and
Page 3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
09/1058 - Change a Development Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 2.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.