Preliminary Erosion & Sediment Control Strategy
Noosa on Weyba
Table 4-4 Sediment Control Measures
Technique Typical Use
Sediment Basin – Type F and D Type 1 sediment trap when suitably sized. Best suited to fine grained, poor settling
or dispersive soils. Can provide turbidity control when appropriately managed.
Sediment Fence Type 3 sediment trap. Suitable for all soil types. Two types of sediment fencing
material are available; woven fabric or non-woven composite fabric. Non-woven
composite fabric type preferred material for fencing adjacent to critical habitats.
Filter Sock Type 2 sediment trap. Suitable for all soil types.
Sediment Trench Type 2 or 3 sediment trap. Appropriate for use in long narrow spaces such as at
the base of fill batters where space is limited between the toe of batter and property
boundary.
Rock Filter Dam Type 2 sediment trap. Can be used where there is sufficient space to construct a
rock embankment. Primary filter medium is either filter cloth or aggregate. Filter
cloth primary filters used where removal of fine grained sediment is critical, however
on-going performance is dependent on regular de-silting and replacement of fabric.
Aggregate filters are generally used in long-term sediment traps as this type of
device is less difficult to de-silt regularly.
Sediment Weir Type 2 sediment trap. Can be used as an alternative to a rock filter dam where
space is limited.
Construction Entry / Exit Points Three main types include rock pad areas, vibration grids and wash bays. Rock pad
areas are suitable for all soil types. Vibration grids are best suited to sandy soils.
For construction near fragile environments, when turbidity control is an issue, or
when working with highly cohesive clays then a wash bay is considered the most
appropriate.
Control measures other than those techniques listed above may also be appropriate for use within the
construction site. Refer to Section 4 of the IECA ‘Best Practice Erosion and Sediment Control (2008)’
guidelines for comprehensive lists of available drainage control, velocity control, erosion control and
sediment control techniques, including the recommended usage of the various measures.
27 September 2013 Cardno 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.