Preliminary Erosion & Sediment Control Strategy
Noosa on Weyba
Based on the size of the proposed disturbed areas and the expected soil losses from the contributing
catchment areas, sediment basins are recommended to be incorporated on-site to assist in capturing
sediments transported via runoff during the construction phase of the development. Based on the
available preliminary development layout, the approximate location and minimum size of the proposed
basins are shown on Cardno Sketch No. 510119/002-SK910 to 912 included in Appendix B. These
sediment basins should be established prior to commencing with significant clearing and bulk earthworks.
All water trapped within the sediment basins is to be tested for compliance with the ‘Discharge
Performance Criteria’ outlined in Section 3 of this report. Where the water does not meet these criteria,
the water is to be held and treated in accordance with this ESCP. Dosing with lime and gypsum may be
required to reach acceptable levels of pH and suspended solids. The lime or gypsum is to be spread
evenly over the entire pond surface. For the characteristics of various flocculating agents refer to Table
B17 from the IECA ‘Best Practice Erosion and Sediment Control (2008)’ guidelines. For sediment basin
management purposes it is recommended that the contractor begin sediment flocculation immediately
following a rainfall event. This will allow maximum time for flocculation to occur to assist in reducing the
runoff holding times. To improve the efficiency and effectiveness of the flocculation process it is
recommended that the contractor undertake trial testing for flocculent rates prior to a rainfall event. The
effectiveness of the flocculent will determine the actual runoff holding times for each basin. The detailed
methods for flocculation and types of flocculants to be used are to be confirmed by the contractor.
It is expected that the sediment basins will also form part of acid sulphate soils management strategy. In
areas where dewatering activities are required, extracted waters shall be directed to the temporary
sediment basins for testing and neutralisation where required. No waters shall be discharged or reused
on-site unless verification testing reveals water quality properties in achievement of the release criteria
outlined in in project acid sulphate soils management plan.
Due to the size and grades of the various disturbed areas, catch drains and diversion bunds will be used
to capture and convey surface runoff to the nominated sediment traps. Where necessary the appropriate
velocity control devices or linings should be incorporated into the drainage channels to reduce flow
velocity and increase the effective scour resistance of the channels.
Clearing and land disturbing activities must not occur until appropriate erosion and sediment control
measures are implemented.
Where practical clearing works should be limited to 2 metres from the edge of any essential construction
activities as outlined on the nominated earthworks plans. As a guide the IECA guidelines outline the
following best practice land clearing limits.
- Clearing should be limited to the area necessary to provide up to eight (8) weeks of site activity during
those months when the expected average rainfall is less than 45mm, six (6) if between 45 and
100mm, four (4) weeks if between 100 and 225mm and two (2) weeks if greater than 225mm.
All vegetation on the site that is selected to be removed is to be mulched / chipped and reused / applied
to cleared areas as an erosion control technique during the bulk earthworks. All disturbed regions will be
reinstated progressively.
Emphasis shall be placed on source control of erosion by retaining vegetation for as long as practical and
revegetating disturbed areas as soon as possible.
The bulk earthworks will be carried out progressively and compacted in stages to prevent large areas of
unconsolidated material being present on the site.
The period of exposure of the earthworks areas should aim to be minimised and pavement and
vegetation cover will be established as quickly as possible.
Soil stabilisation measures such as mulching, turf or other landscaping shall be provided as soon as
possible after construction is completed.
All erosion and sediment control devices must be maintained to be fully operational at all times. Worn,
damaged or otherwise defective materials and components are to be repaired, refurbished or replaced as
they become ineffective for their design purpose.
27 September 2013 Cardno 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.