Preliminary Erosion & Sediment Control Strategy
Noosa on Weyba
All sediment control structures must be operated and maintained in an effective operational condition.
These structures must not be allowed to accumulate sediment volumes in excess of forty per cent (40%)
sediment storage design capacity. Where sediment basins are used a marker shall be placed within the
basin to show the level above which the design capacity occurs. Materials removed from sediment
retention devices must be disposed of in a manner approved by the consent authority that does not cause
pollution.
Any chemicals (including lime or gypsum) or fuel / oil stored on site shall be stored under cover in a
bunded area or placed sufficiently above ground level to preclude contamination of surface water. The
only potential source of contamination of surface water is to be due to erosion of ground surfaces.
Should it be deemed necessary from monitoring, the Contractor shall install additional measures to
ensure the objectives of this element are met and to minimise the impact of construction activities on the
surrounding environment.
6.4 Monitoring
As a minimum the following monitoring should be carried out during the construction phase to confirm
compliance as follows:
Inspection of any disturbed / filled areas for their potential erosion susceptibility and treat in accordance
with the practices in the IECA ‘Best Practice Erosion and Sediment Control (2008)’ guidelines.
Regular (daily) inspections of erosion protection measures.
Inspections during or following each significant rainfall event for erosion incidence. During each
significant intense rainfall event, the turbidity of stormwater runoff exiting the site shall be visually checked
to ascertain whether the control measures meet the criterion.
6.4.1 Sediment Basin Monitoring
Testing of Suspended Solids and pH within any temporary sediment basins is to occur prior to any
discharges.
Testing of turbidity within the temporary sediment basins and the receiving waters is to be performed prior
to the controlled discharging of the trapped runoff contained within the sediment basins. If the turbidity of
the runoff trapped within the sediment basin is greater than 10% above the receiving waters further
dosing with the appropriate flocculent is required until acceptable levels are reached.
Where the sediment basin is being utilised as part of the on-site acid sulphate soils management
strategy, additional water quality monitoring may be required in order to satisfy the release criteria for
stored runoff in accordance with the project acid sulphate soils management plan.
6.5 Responsible Person / Organisation
The Contractor is generally the responsible party for all of the above items. This includes compliance with
the criteria outlined in Section 3, implementation and monitoring of the erosion and sediment control
measures, reporting and any corrective action which may result from the non-compliance with the ESCP and
conditions of approval.
6.6 Reporting
It is recommended that a weekly check sheet be filled out and monthly reports, including any testing results,
are prepared by the Contractor. The monthly reports should contain information on the performance of the
erosion and sediment control devices and any water quality monitoring results and a brief description of the
same (including any incidences of non-compliance and corrective actions implemented).
Immediate notification of system failure should be made to the Developer with significant failures that have
the potential to cause environmental harm to be notified to the Sunshine Coast Council.
27 September 2013 Cardno 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 8- Amended Engineering Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 61.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.