Attachment 8- Amended Engineering Report MCU12/0208

of 109

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (61.0 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 67, section 1. The text section number identifies this passage in the reader.

                                                                          Preliminary Erosion & Sediment Control Strategy
                                                                                                       Noosa on Weyba



   All sediment control structures must be operated and maintained in an effective operational condition.
   These structures must not be allowed to accumulate sediment volumes in excess of forty per cent (40%)
   sediment storage design capacity. Where sediment basins are used a marker shall be placed within the
   basin to show the level above which the design capacity occurs. Materials removed from sediment
   retention devices must be disposed of in a manner approved by the consent authority that does not cause
   pollution.
   Any chemicals (including lime or gypsum) or fuel / oil stored on site shall be stored under cover in a
   bunded area or placed sufficiently above ground level to preclude contamination of surface water. The
   only potential source of contamination of surface water is to be due to erosion of ground surfaces.
   Should it be deemed necessary from monitoring, the Contractor shall install additional measures to
   ensure the objectives of this element are met and to minimise the impact of construction activities on the
   surrounding environment.

6.4          Monitoring
As a minimum the following monitoring should be carried out during the construction phase to confirm
compliance as follows:
   Inspection of any disturbed / filled areas for their potential erosion susceptibility and treat in accordance
   with the practices in the IECA ‘Best Practice Erosion and Sediment Control (2008)’ guidelines.
   Regular (daily) inspections of erosion protection measures.
   Inspections during or following each significant rainfall event for erosion incidence. During each
   significant intense rainfall event, the turbidity of stormwater runoff exiting the site shall be visually checked
   to ascertain whether the control measures meet the criterion.

6.4.1        Sediment Basin Monitoring
   Testing of Suspended Solids and pH within any temporary sediment basins is to occur prior to any
   discharges.
   Testing of turbidity within the temporary sediment basins and the receiving waters is to be performed prior
   to the controlled discharging of the trapped runoff contained within the sediment basins. If the turbidity of
   the runoff trapped within the sediment basin is greater than 10% above the receiving waters further
   dosing with the appropriate flocculent is required until acceptable levels are reached.
   Where the sediment basin is being utilised as part of the on-site acid sulphate soils management
   strategy, additional water quality monitoring may be required in order to satisfy the release criteria for
   stored runoff in accordance with the project acid sulphate soils management plan.

6.5          Responsible Person / Organisation
The Contractor is generally the responsible party for all of the above items. This includes compliance with
the criteria outlined in Section 3, implementation and monitoring of the erosion and sediment control
measures, reporting and any corrective action which may result from the non-compliance with the ESCP and
conditions of approval.

6.6          Reporting
It is recommended that a weekly check sheet be filled out and monthly reports, including any testing results,
are prepared by the Contractor. The monthly reports should contain information on the performance of the
erosion and sediment control devices and any water quality monitoring results and a brief description of the
same (including any incidences of non-compliance and corrective actions implemented).
Immediate notification of system failure should be made to the Developer with significant failures that have
the potential to cause environmental harm to be notified to the Sunshine Coast Council.




27 September 2013                                     Cardno                                                          10

Used in these records

About this file

File size
61.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8- Amended Engineering Report MCU12_0208.pdf · 61.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗