                                                                        Preliminary Acid Sulphate Soil Management Plan
                                                                                                        Noosa on Weyba


7.10          Earthworks
In areas where excavations may disturb potential or actual ASS, testing shall occur to determine the liming
rate. Acidic materials shall be neutralised in situ prior to any transport within the site.

7.10.1        Excavated Materials
Materials gained from excavation in areas identified as containing existing or potential ASS shall be treated
to ensure the neutralisation of any acidic soils in situ where possible (refer to Section 7.11.1). Prior to
excavation, the required amount of neutralising agent determined by the geotechnical practitioner shall be
applied to the area to be excavated. The area shall be turned or ploughed with machinery to ensure
adequate mixing of neutralising agent has taken place.

7.10.2        Fill Areas
It is assumed that areas to be filled will be stripped of topsoil to a maximum of 0.5 metre depth. All topsoil
materials will require testing and treatment where required. Materials to be stockpiled shall be treated prior to
stockpiling refer to Section 7.14 for detailed information on stockpiling.

7.11          Neutralisation
The Contractor may choose to adopt the liming rates that will be provided by in the detailed Acid Sulphate
Soils Management Plan or alternatively choose to undertake further analysis of the materials during
construction to allow the adoption of more refined liming rates arising from those investigations. If the
Contractor chooses to conduct independent sampling, this must be done in consultation with a geotechnical
practitioner and all records of sampling and chain of custody must be retained on site in a manner suitable
for presentation for compliance. Where further testing is conducted to refine liming rates, existing results
must be incorporated into the calculations.

7.11.1        Treatment Area Preparation
Where neutralisation is required and in situ treatment is not possible the neutralisation of acidic materials
shall be undertaken on a suitably prepared treatment pad, designed to the following specifications.
          A layer of compacted non-ASS clayey material (0.3-0.5 metre depth) shall be placed on the
           treatment pad surface to restrict infiltration into the surrounding soil and ground water;
          A guard layer shall be placed over the compacted clay cap to ensure any leachate generated in the
           treatment pile is treated. The guard layer shall comprise of neutralising agent to a minimum of 5kg
           per square metre; and
          Treatment pads shall be bunded and fitted with diversion drains. All drains and bunds shall be
           treated with a guard layer.
Reapplication of the guard layer and compaction of the clay cap may be required where these provisions are
affected by mixing.

7.11.2        Excavated Materials
All excavated materials shall be tested and neutralised, where required, with agricultural lime at the
calculated rate determined by the geotechnical practitioner. Treatment shall be undertaken in situ or on a
suitably prepared treatment pad as outlined in Section 7.11.1. Acidic materials shall be placed in 150-300
mm thick layers over the guard layer for drying. The calculated amount of neutralising agent shall be spread
over the materials once dry. Acidic materials may require reworking to achieve the desired mixing and
drying.
Guard layers shall be placed between each layer of ASS to minimise the potential for leachate to be
exported from the treatment area.
Following neutralisation, treated materials shall be validated prior to final placement. Validation requirements
are outlined in Table 7-3.




10 October 2013                                      Cardno                                                        17

Used in these records

About this file

File size
61.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8- Amended Engineering Report MCU12_0208.pdf · 61.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.