Project No. 306-2474
November, 2006                                                                        Page 7
                                                                                     Page 7
      It is recommended that the designers satisfy themselves that the use of AS.2870 is
     applicable for the proposed design.
     6.4.2.   High Level Footings
     Given the proposed scope of excavation for the basement floor, a high level foundation
     system may be suitable for this development.
     The base of all footings should be individually recompacted using a vibrating plate
     compactor prior to placement of reinforcing steel and concrete as soils may be loosened
     during the excavation process by machinery action. If the sand is dry, it should be
     saturated and left for a short period prior to vibration.  Should any loose areas be
     encountered in the footing excavations the density of these areas must be improved.
    Table 3 outlines allowable bearing capacities for high level footings on the site.
    TABLE 3     ALLOWABLE BEARING CAPACITIES FOR HIGH LEVEL FOOTINGS

        ~~   Sand            -Medium Dense     | ~~~ 400                   “450.—~~”
                          - Dense to Very Dense         150                 225
    6.4.3.   Construction Considerations
    Inspections
    It is recommended that inspections be undertaken by an experienced and qualified           @
    geotechnical engineer following footing excavations to confirm the adequacy of the
   founding soils.  Inspections should be carried out prior to placement of reinforcing steel
   and ordering of concrete.
   Underground Services
   Where footings are located adjacent to underground services, the footings should extend
   to base a minimum of 300mm below the trench base level for a distance of 1.0m out from
   the trench. Beyond 1.0m, the footings should be taken a minimum of 300mm below an
   imaginary line drawn up at 30° from the trench base level. Figure 1 refers.
   These requirements do not override minimum footing base levels.

                                                      GH SOIL SURVEYS ENGINEERING

Used in these records

About this file

File size
4.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015584F.001.pdf · 4.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.